Trench Safety and Utility Trenching
Reviewed by a working tradesman with 17+ years in the field.
Some links on this site are affiliate links. If you buy through them we may earn a commission at no extra cost to you. Affiliate disclosure
The rules and habits that decide when you can step into a trench, and how the walls are kept up.
Tap your level and the boxes below open to the advice for you. Remembered on this device.
By the end you can
- Say what a trench is, when protection is required, and why 1.2 m (4 ft) is your own no-entry line.
- Name the four ways to make a trench safe, and who chooses and builds them.
- Name the things that bring a trench down, and run the daily check.
- Start with a locate request, and know that private lines are not covered.
- Find your province's numbers in the regulation instead of trusting a summary.
A trench wall can look solid right up until it fails, and a cubic metre of soil weighs well over a tonne. A person caught in a cave-in is buried fast and cannot dig out. Treat 1.2 m (4 ft) as your own no-entry line anywhere in Canada: no one goes in until a qualified person has sloped, benched or supported the sides. Soft, wet, flooded or loaded ground can fail at any depth. If you are unsure, do not enter.
The big idea
Trench safety is a worker-safety matter set by your provincial or territorial OHS regulator (WorkSafeBC in BC), not by NBC 2020 Part 9. So trigger depths, spoil distances and engineer thresholds differ by province. This page uses BC and Alberta as the worked examples, because their regulations were read for this page, and the By Province box shows what the others say.
Most trench deaths happen in trenches that were "only a few feet deep". Everything below is about keeping the walls where they belong and keeping people out until they are safe.
When the rules kick in
- BC: a trench is an excavation less than 3.7 m (12 ft) wide at the bottom, over 1.2 m (4 ft) deep, and of any length (OHS Reg. s. 20.1). Workers may not enter a trench deeper than 1.2 m unless the sides are sloped or supported as Part 20 requires (s. 20.81).
- Alberta: protection is required before entry into a trench over 1.5 m (about 5 ft) deep unless it is cut back (OHS Code Part 32; the regulator's explanation guide cites s. 446 and s. 450).
- Other provinces: 1.2 m (4 ft) in SK, ON, NB, NS, NL, PE and YT; 1.5 m in AB and MB. See the By Province box.
- Under the trigger depth the hole still has to be safe. Soft, wet, flooded or loaded ground can fail at any depth.
The BC sloping ratios and shoring tables, and Alberta's exact trench definition, are in the regulation text. Take them from the regulator's own document for your job, not from a summary, including this page.
When you need an engineer
Some excavations need written instructions from a qualified registered professional, usually a geotechnical or civil engineer. In BC (OHS Reg. s. 20.78) that includes an excavation:
- deeper than 6 m (20 ft)
- next to a building or other structure
- subject to vibration or hydrostatic (water) pressure that could cause hazardous movement
- where the ground slopes away from the edge steeper than 3 horizontal to 1 vertical
In BC, shoring that is a support structure needs an engineer, and end shoring with walers longer than 1.8 m (6 ft) needs engineer design (s. 20.78 and 20.81(4)). Yukon has a similar list. Alberta requires a professional engineer to design and certify temporary protective structures for excavations deeper than 3 m (10 ft) (s. 456).
Note the second item: digging beside an existing house, garage or retaining wall puts you in engineer territory even in a shallow trench. That catches a lot of renovation crews out.
Call before you dig
- Locate underground utilities before you excavate. Start with your province's one-call centre.
- Lead times: BC 1 Call, 3 full business days, 1-800-474-6886. Alberta One-Call, 3 full business days, 1-800-242-3447. Manitoba, 1-800-940-3447, contact within 3 business days. Quebec, Info-Excavation, 4 working days. Saskatchewan, 2 working days per SaskEnergy.
- Private lines on the property are not covered by a locate request.
- Never probe for buried gas or electrical lines with pointed tools. Hand-dig or vacuum-excavate within the utility owner's required distance.
- Remove or secure trees, poles and boulders next to the dig if they could endanger workers.
Check the one-call centre's website for the current process and lead time, and whether a locate is legally required for a homeowner where you live. Ontario One Call lead time and Saskatchewan's request process were not re-verified for this page.
Soil under the trench rules
Alberta's code classifies trench soil into three types (s. 442): hard and compact, likely to crack or crumble, and soft, sandy or loose. Ontario uses four types, Type 1 to Type 4. Whatever the system, the soil is described by how it behaves, not by what it is called.
- Firmest: hard and solid, holds its shape
- Middle: likely to crack or crumble
- Weakest: soft, sandy, filled or loose
Wet, disturbed, previously dug or vibrated ground is weaker than it looks. Treat fill and backfilled ground as the weakest class. Soft or saturated clay can be as bad as loose sand. When in doubt, treat the soil as the weakest class, or get a competent person to assess it.
Your options: slope, bench, shore or box
Before anyone goes in, the sides must be sloped, benched or supported. Common ways:
- Sloped as a qualified professional specifies, or at the angles your regulation allows for the soil.
- Benched as your regulation shows.
- Shored to the minimum requirements in your regulation's tables, or to an engineer's design.
- Protected by a manufactured trench box or shoring cage, used within the maker's limits.
Choosing and building any of these is a job for a qualified person or an engineer, not for a homeowner. Install shoring from the top down and remove it in reverse order.
BC's slope ratios, shoring tables, end-shoring rules and timber grades are in Part 20 and Table 20-1. They were not re-read for this page, so they are not quoted here. Use the regulator's document.
Getting in and out
Workers need a safe way in and out of every trench, reachable quickly from where they are working, and a ladder must extend above the edge so you can step off.
- Alberta: in a trench over 1.5 m (5 ft) deep, the exit may be no more than 8 m (26 ft) from the worker (s. 455).
- NB and NS: ladder at least 1 m (3 ft 3 in) above the edge and within 15 m (50 ft) of the worker. PE: at least 3 ft (914 mm) above and no more than 50 ft (15 m) from workers. NL: at least 0.91 m (3 ft) above.
- Keep the ladder clear of debris, tools and hoses.
Worked example (Alberta). A trench 1.8 m (6 ft) deep and 40 m (131 ft) long. A ladder serves 8 m either side, so one ladder covers 16 m (52 ft). 40 ÷ 16 = 2.5, so you need at least 3 ladders, spaced so no one is more than 8 m from one.
BC's ladder distance and height above the edge are set in s. 20.87 and are not quoted here until checked against the regulation.
Why trenches collapse
- Water softens walls and builds pressure behind them
- Spoil piles, stored materials and equipment load the edge. Alberta requires spoil at least 1 m (3 ft 3 in) from the edge, and the pile slope no steeper than 45 degrees (s. 453).
- Vibration from machines, traffic and compactors shakes loose soil down
- Frost leaves hidden cracks that open as the ground thaws
- Digging next to older trenches, utilities or fill (soil already disturbed)
- Undercutting the wall by over-excavating at the bottom
- Soil changing partway down without anyone noticing
Daily checks
- Check the trench before the first person goes in, every shift
- Check again after rain, thaw or heavy frost
- Check after anything vibrates the ground or loads the edge
- Check when the soil changes or water starts to seep
Cracks parallel to the trench, sloughing, bulging walls or new seepage mean everyone gets out and nobody goes back in until the problem is fixed. Alberta also requires that workers not enter until hazardous accumulations of water are eliminated (s. 445). Keep a short written log of what you checked and when. It is cheap protection if anyone ever asks.
Utility trenching
Depth of cover, separation between services and bedding for water, sewer, gas, electrical and communications lines are set by the utility owner and your municipality, not by one national number. Cover depth depends on local frost depth, traffic loads and pipe material.
- Get the servicing requirements from the municipality or utility before you cut the trench.
- Plumbing that serves the building follows your provincial plumbing code and the municipality's requirements.
- Electrical service depths come from the Canadian Electrical Code as adopted in your province, and the utility. Gas work needs a certified gas contractor.
- Bed pipe as the manufacturer and the municipality specify. Keep sharp rock out of the pipe zone.
- Backfill in lifts, free of organics, and protect the pipe zone while compacting (see Backfill and Lift Thickness).
Notes from the trade
Never trust soil you have not watched for a few minutes. A fresh cut often stands for a while and then lets go all at once. Have the trench box on site before you need it, and have a trained crew set it before the first person steps in. Never be in the trench while the box is moved, never work on the open side of a box, and check the box height against the trench depth.
Where it rains for long spells, the ground fills with water, so a trench that was fine on Monday can be unsafe on Friday. Where the ground freezes, frost hides cracks and weak layers that open on the first warm day. Dry heat crusts the wall while the soil behind stays loose. Re-inspect after any weather change.
This is a regulation issue first and a building code issue second. Inspectors can stop work and the regulator can issue penalties. Homeowner rules differ by province. In BC, a homeowner must register with WorkSafeBC if a one-time project reaches 24 or more total hours, or ongoing work runs 8 or more hours a week. In Ontario the Act does not apply to work done by the owner or occupant on a private residence, but an owner who hires several contractors with no general contractor is likely the "constructor". In NB and NS the owner is deemed the constructor where no constructor controls the work. Confirm before you hire anyone.
Your trench is 1.3 m deep. In BC, is it a trench, and may you step in to check the bottom?
In Alberta a trench is 1.8 m deep and 40 m long. Ladders must be within 8 m of the worker. How many ladders at least?
The excavator operator puts the spoil pile 0.5 m (20 in) from the edge. Is that acceptable?
You find a hairline crack running parallel to the trench, 600 mm (2 ft) back from the edge. What now?
It rained all night. The trench was fine yesterday. May the crew start work?
The trench is next to an existing garage wall. Does depth alone decide whether you need an engineer?
- Must-haveLocates: locate paint or flags from the utility, spray paint, a measuring tape and a flat-blade hand shovel (never a pointed probe near gas or electric lines)
- Rent itExcavating by machine: an excavator or backhoe with a skilled operator
- Must-haveExcavating by hand:
- Rent itProtecting the trench:
- Must-haveGetting in and out:
- Must-haveKeeping people away:
- Rent itWater:
- Must-havePPE:
Home DIY
Laborer or helper
1st-year apprentice
Apprentice, 2nd to 4th year
Journeyperson
Lead hand or foreman
Contractor or business owner
Starting a new business
There is no national trench rule. Each province and territory sets its own trigger depth, slopes and engineer thresholds in its OHS regulation. Figures marked (summary) come from a secondary compilation of the regulations, not the regulation text, so confirm them before relying on them.
- BC: OHS Reg. Part 20. Trench over 1.2 m (4 ft) deep and under 3.7 m (12 ft) wide (s. 20.1). Protection over 1.2 m (s. 20.81). Engineer or qualified professional triggers in s. 20.78.
- AB: OHS Code Part 32. Protection over 1.5 m (5 ft). Spoil at least 1 m (3 ft 3 in) back, pile slope 45 degrees or less (s. 453). Exit within 8 m (26 ft) over 1.5 m depth (s. 455). Engineer design over 3 m (10 ft) (s. 456).
- SK: OHS Regulations, 2020, Part 17. Trigger 1.2 m per the regulator's guide. Spoil 1 m back (summary).
- MB: WSH Regulation Part 26. Notice for excavations over 1.5 m (5 ft) that workers enter. Support or slope over 1.5 m per the WCB guide. Confirm.
- ON: O. Reg. 213/91. Support unless under 1.2 m (4 ft), sloped by soil type, or an engineer's opinion. Spoil 1 m back and ladders per ss. 233 and 240.
- QC: CNESST Safety Code. Excavation 1.2 m or deeper. Spoil 1.2 m (4 ft) from the rim, vehicles 3 m (10 ft) back unless reinforced shoring. Ladders every 15 m (50 ft) (summary).
- NB: shoring over 1.2 m. Spoil 1.2 m back. Ladder 1 m above, within 15 m of the worker (summary). NS: over 1.2 m. Spoil at least 1 m unless an engineer certifies less (summary). PE: over 4 ft (1,219 mm). Spoil 2 ft (609 mm). NL: 1.22 m (4 ft). Spoil 1.22 m for trenches (summary).
- YT: over 1.2 m. Engineer for over 6 m (20 ft) or permafrost (summary). NWT and NU: spoil 1 m; confirm the trigger depth with the regulator. No territory-wide one-call in the Yukon: call each utility.
See Canada by Province for the full comparison.
- WorkSafeBC, OHS Regulation Part 20 (s. 20.1 trench definition; section titles 20.78 to 20.89)
- Alberta OHS Code, Part 32 Excavating and Tunnelling (section list)
- Alberta OHS Code Explanation Guide, Part 32 (the 2009 guide; the 1.5 m, 1 m, 8 m and 3 m figures)
- OHS Insider, Excavation and trenching: know the laws of your province (secondary compilation for BC 20.78 and 20.81, and the other provinces)
- One-call centres: BC 1 Call, Alberta One-Call, Click Before You Dig Manitoba, Info-Excavation, SaskEnergy.
- CSA Z94.1, Z94.3, Z195 and Z11 for PPE and ladders. Check current editions.