Putting steel bars in the right size, place, length and cover before the concrete hides them.
Tap your level and the boxes below open to the advice for you. Remembered on this device.
By the end you can
- Read a Canadian bar size (10M, 15M, 20M, 25M) and know its diameter and weight.
- Explain cover and why steel sits on supports, not on the ground.
- Work out bar counts and weights from spacing and length.
- Place, splice and tie bars for footings, walls, slabs, stairs and retaining walls.
- Check the steel before the inspector does.
Exposed rebar ends are an impalement hazard, and a fall onto vertical bars can kill. Cap or guard vertical bar ends where people work above or beside them, and check your provincial OHS regulator for the rule. Brace tall mats and cages so they cannot topple, and use proper lifting gear, gloves and eye protection when cutting and bending steel.
The big idea
Concrete is strong when squeezed and weak when pulled. Rebar takes the pull. It only works if it is in the right place, the right size, the right length and covered with concrete on every side. Once the concrete is in, nobody can see it, so the inspection before the pour is the only check there ever is.
Purpose of rebar
- Takes tension that concrete cannot carry
- Controls cracking from shrinkage and load
- Ties footings, walls, slabs and stairs together
- Strengthens corners, openings and transitions
Rebar sizes and types in Canada
Canadian bars are named by an "M" number that is close to the diameter in millimetres, and the bars are made to CSA G30.18.
| Bar | Diameter | Area | Mass |
|---|---|---|---|
| 10M | 11.3 mm (0.44 in) | 100 mm² | 0.785 kg/m (0.53 lb/ft) |
| 15M | 16.0 mm (0.63 in) | 200 mm² | 1.570 kg/m (1.06 lb/ft) |
| 20M | 19.5 mm (0.77 in) | 300 mm² | 2.355 kg/m (1.58 lb/ft) |
| 25M | 25.2 mm (0.99 in) | 500 mm² | 3.925 kg/m (2.64 lb/ft) |
| 30M | 29.9 mm (1.18 in) | 700 mm² | 5.495 kg/m (3.69 lb/ft) |
| 35M | 35.7 mm (1.41 in) | 1,000 mm² | 7.850 kg/m (5.27 lb/ft) |
- 10M and 15M are the common house-and-small-building bars. 25M and up is commercial, industrial and civil work.
- Old US sizes on older drawings are not the same. A US #4 is 1/2 in (12.7 mm), smaller than 15M (16.0 mm). Do not swap them.
- Grade: normally 400 MPa, either weldable (400W) or regular (400R). Use what the drawings call for.
- Coated or special steel: epoxy-coated, galvanized or stainless where the drawings require it for corrosion.
The sizes above are from a secondary table that matches the usual CSA G30.18 values. Check them against the standard and the bar schedule on your drawings. Never swap a bar size or grade without the engineer's approval.
Concrete cover
Cover is the concrete between the steel and the outside face. It stops water and air reaching the steel and protects it in a fire. More exposure means more cover.
- Cast against soil (footings): commonly 75 mm (3 in).
- Interior slabs: as little as 20 mm (3/4 in).
- Formed faces exposed to weather or soil (walls, exterior slabs): in between, depending on bar size and exposure.
Example. Bottom steel in a footing cast on soil with 75 mm cover sits on chairs 75 mm (3 in) high.
The 75 mm and 20 mm figures are quoted in a secondary summary of CSA A23.1 Table 17. The in-between values were not verified. Cover depends on bar size, exposure class and member type (CSA A23.1 and A23.3). The engineer's drawings and the code decide for your job.
Bar supports
- Plastic chairs under mesh and bars in slabs
- Concrete blocks (dobies) under footing bars
- Continuous chairs for mats and heavy bars
- Wall spacers to keep bars off the form face
- Never use wood, rocks, bricks or debris (see Rebar Chairs and Spacers)
Counting bars and weight
Bars at a spacing along a length: spaces = length ÷ spacing, and bars = spaces + 1. Weight = total length × mass per metre.
Wall. A 12 m (39 ft 4 in) wall with vertical 15M bars at 400 mm (15 3/4 in) on centre: 12 ÷ 0.4 = 30 spaces, so 31 bars. At 2.4 m (7 ft 10 in) each that is 74.4 m, and 74.4 × 1.57 = 116.8 kg, about 257 lb.
Footing. Two continuous 15M bars along a 30 m (98 ft) footing: 60 m × 1.57 = 94.2 kg, about 208 lb, before laps and waste.
The spacing and bar size here are examples. The drawings or the bar schedule give yours.
Where the steel goes
Footings
Many house footings are unreinforced under Part 9, so do not add or leave out bars on your own. Follow the drawings: longitudinal bars in the middle of the width on supports, tied to the dowels that connect the wall, corner bars at every turn, splices at the length the drawings give.
Foundation walls
Vertical bars tied to the footing dowels, horizontal bars at the specified spacing, extra bars around openings and at corners, and spacers to hold cover on both faces.
Slabs and pads
Welded wire mesh or bars, as drawn, on chairs at the height the drawings say, with perimeter bars at thickened edges and dowels where the slab ties into a wall.
Stairs and landings
Bars in the treads and risers, landing mats tied into the stair steel, dowels to tie to slabs or walls, and extra bars at nosings.
Retaining walls
Vertical bars closer together near the bottom, horizontal bars as drawn, corner bars at turns and steps, and top bars for caps or slab connections.
Lap splices and tying
A splice passes the load from one bar to the next. A splice that is too short is a weak link you cannot see.
- Use the splice length on the drawings. It depends on bar size and concrete.
- Stagger splices where you can, and do not splice in high-stress locations unless designed.
- Tie the splice at both ends.
- Use tie wire and a tying tool, firm but not so tight the bar moves out of position.
- Keep wire ends turned away from the form face, and make sure bars cannot shift while concrete goes in.
Alignment and inspection
- Check spacing with a tape.
- Check cover at several points, at corners and at openings.
- Straight, level bars, held up by supports.
- Dowels aligned for the wall or column above.
- Look at every corner and opening.
Common mistakes
- Rebar touching soil or the form
- Wrong spacing
- Missing corner bars
- Splices too short
- Rebar floating or pushed down during the pour
- Missing or misaligned dowels
- Wrong bar size or grade
Concrete hides everything, so check twice before the pour. Bars are easier to adjust at the dowels than at the pour. Spend extra time at corners and openings, because that is where cracks start.
Cold makes steel stiffer and harder to bend. Mud on bars can hurt the bond, so clean off mud, oil and form release before the pour. Hot sun can overheat plastic chairs.
Bar size and spacing, cover, splices, dowels, corners and openings, and whether the steel matches the drawings. The inspection happens before the pour, so book it ahead.
A drawing says 15M bars. What is the nominal diameter, and is it the same as a US #4 bar?
Two continuous 15M bars run the length of a 30 m (98 ft) footing. What do they weigh, before laps and waste?
A 12 m (39 ft 4 in) wall has vertical 15M bars at 400 mm (15 3/4 in) on centre. How many bars?
A footing is cast against soil. What cover is commonly used, and how high is the chair?
The bars look right but one footing dowel is 40 mm (1 1/2 in) out of position. What do you do?
What hazard is on every vertical bar end?
- Must-haveLayout and measuring:
- Must-haveCutting: bolt cutters or a hand rebar cutter for 10M and 15M bars (have heavier bars cut and bent by the supplier to the bar schedule)
- Must-haveBending: a hand bar bender (hickey) and a bending bench for field bends the drawings allow
- Must-haveTying:
- Must-haveSupports:
- Must-haveProtection: rebar caps or guards on vertical bar ends where people work above or beside them
- Must-haveChecking:
- Must-havePPE: hard hat (CSA Z94.1), safety glasses (CSA Z94.3), green-triangle boots (CSA Z195), gloves and hearing protection, cut-resistant where possible, plus CSA Z259 fall arrest where work is at 3 m (10 ft) or more
Home DIY
Laborer or helper
1st-year apprentice
Apprentice, 2nd to 4th year
Journeyperson
Lead hand or foreman
Contractor or business owner
Starting a new business
Reinforcing steel in Canada is made to CSA G30.18. Cover and splices come from CSA A23.1 and A23.3 and from the engineer's drawings, and house foundations follow NBC Part 9 as each province adopts it. Rebar capping and fall protection are provincial OHS matters.
- All provinces and territories: the bar sizes and the drawings are the same. Ask your local authority when reinforcement is inspected, and your provincial OHS regulator about capping vertical bars.
- See Permits and Approvals for the inspection stops, and Canada by Province for the comparison.
- Engineering ToolBox, reinforcing bar sizes (secondary table; check against CSA G30.18)
- Building Club, Concrete structures checklist (cover of 75 mm against soil and 20 mm interior, citing CSA A23.1 Table 17; a secondary summary)
- CSA G30.18, A23.1 and A23.3 are paid standards. Check current editions.
- Bar counts and weights are arithmetic, calculated and re-checked.