Slab and Pad Forms

Written for Canada. Plans are metric, but many crews and suppliers work in feet and inches, so this site gives both: millimetres and metres, with feet and inches beside them. Codes are the National Building Code of Canada 2020 (NBC 2020) Part 9 as your province adopts it. A number marked Confirm has not been checked against every province, so check it with your own authority before you act on it.

Reviewed by a working tradesman with 17+ years in the field.

Some links on this site are affiliate links. If you buy through them we may earn a commission at no extra cost to you. Affiliate disclosure

The base, edge forms, steel and joints that set a slab's level, thickness and cracking.

I am a:

Tap your level and the boxes below open to the advice for you. Remembered on this device.

What it isThe base, edge forms, steel and joints that set a slab's level, thickness and cracking.
Why it mattersA slab shows every mistake. Fixing one afterwards usually means a saw and a jackhammer.
Minimum thickness75 mm (3 in) in the model code. The drawings can ask for more.
AlwaysFirm, dry, unfrozen base, and steel up on chairs.

By the end you can

  • Tell slabs on grade, structural slabs, exterior slabs and equipment pads apart.
  • Prepare a base, choose a form board tall enough, and set forms to grade.
  • Lay out control and isolation joints for a slab.
  • Work out volume and the drop for a drainage slope.
  • Say when to hold the pour.
Stop and read

Do not pour concrete on a wet, soft or frozen base, and do not put electrical, gas or plumbing under a slab yourself. Pipes under a slab are covered by the drawings and the permit. If you are working in a hole or beside a deep footing trench, the trench rules apply (see Trench Safety). Wet concrete burns skin, so wear waterproof gloves and boots and wash it off at once.

The big idea

Slab forms hold the edges and the level of the concrete. A slab shows every mistake: a 10 mm (3/8 in) high spot, a wrong slope, a bar sitting on the dirt. Get the base, the edges and the steel right before the truck arrives.

Types of slabs and pads

A cutaway of a slab on grade. From the bottom: compacted subgrade, compacted granular base, a polyethylene vapour barrier, and the concrete slab with mesh or rebar held up on chairs. A form board and stake hold the edge.
A slab on grade. From the bottom: compacted subgrade, compacted granular base, a polyethylene vapour barrier where required, and the concrete slab with mesh or rebar held up on chairs. Form boards and stakes hold the edge. Thickness, base depth and barrier come from the drawings and the code. Not to scale.
  • Slabs on grade: basement floors, garage floors, and crawl-space or utility slabs.
  • Structural slabs: engineered, with rebar mats or beams. Built to the drawings.
  • Exterior slabs: sidewalks, patios and driveways. These see frost, salt and weather.
  • Equipment pads: pads for heat pumps, generators and pumps, set level.
  • Thickened-edge slabs: slab edges thickened to act as footings.

Under the model code (NBC Part 9, Section 9.16, read in the Vancouver Building Bylaw 2014):

  • Concrete slabs are at least 75 mm (3 in) thick, not counting any topping (9.16.4.3).
  • A drainage layer is required below floors-on-ground, except below slabs in garages, carports or accessory buildings (9.16.2.1). The text I read gives no thickness for it, so take it from the drawings and your province's code.
  • Dampproofing and waterproofing follow Section 9.13 (9.16.1.4).
  • Where floor drains are required, the floor must slope so no water can accumulate (9.16.3.3). No slope value is given.
Confirm

Minimum strengths for interior floors, garage floors and exterior steps, and the air entrainment for freeze-thaw, are on the Concrete Mathematics page. Check the article numbers and the edition your province adopts, and whether insulation under the slab is required where you are.

Base preparation

A slab is only as good as what is under it.

  • Strip topsoil, roots and organic material.
  • Compact the subgrade. Replace soft spots with compacted granular fill.
  • Place and compact the granular base to the thickness in the drawings.
  • Fine-grade the base so slab thickness is even.
  • Place the vapour barrier where required, lapped and taped at joints.
  • Place insulation where the drawings call for it (heated, frost-protected or energy-code slabs).

Forming materials

  • Dimensional lumber: the form board must be at least as tall as the slab is thick. A 38 x 89 mm (2x4) is only 89 mm (3 1/2 in) tall, so for a 100 mm (4 in) slab use a 38 x 140 mm (2x6).
  • Stakes (wood or steel), tight to the form and driven below the top.
  • Form pins and clamps for commercial work.
  • String line and laser for elevation.
  • Form release (optional) so boards come off cleanly.

Building slab and pad forms

  1. Snap lines. Mark the edges and the joint layout.
  2. Set the form boards. To the line and the elevation.
  3. Stake them. Tight, so they will not move under screeding.
  4. Check the elevation. Laser or level along the full perimeter.
  5. Set the reinforcement. Mesh or rebar on chairs, at the height the drawings specify.
  6. Install isolation joints. At walls, columns and anything fixed.
  7. Final walk. Thickness, slope, reinforcement, joints and bracing.

Reinforcement

Welded wire mesh or rebar, as the drawings specify. Many house slabs on grade are unreinforced, so do not add or leave out steel on your own.

  • Rebar mats for structural slabs
  • Extra bars at thickened edges and around openings
  • Chairs, not bricks. Steel on the ground does nothing, and mesh walked into the base does nothing either.

Control, isolation and expansion joints

Concrete shrinks as it cures. Joints decide where it cracks.

  • Control joints: a weakened line that makes cracking happen where you want it. The Portland Cement Association guidance says maximum spacing is 24 to 36 times the slab thickness, with panels square or nearly so (length no more than 1.5 times width), and the groove at least 1/4 of the slab thickness and not less than 25 mm (1 in) deep.
  • Isolation joints: a separation around columns, walls and anything that moves differently from the slab, using a premoulded filler such as asphalt-impregnated fibre or compressible foam.
  • Expansion joints: used between large exterior slabs and fixed structures, as drawn.

Worked example. A 100 mm (4 in) slab: 24 × 0.1 = 2.4 m and 36 × 0.1 = 3.6 m (8 to 12 ft). On a 6 m × 6 m (20 ft × 20 ft) slab, cut joints at 3 m (10 ft) both ways to make four 3 m × 3 m panels. The groove is at least 100 ÷ 4 = 25 mm (1 in) deep.

Saw-cut timing depends on the method: early-entry dry cutting 1 to 4 hours after finishing, conventional wet sawing 4 to 12 hours after, per the same guidance. Keep joints straight, clean and continuous.

Elevation and drainage

  • Garage slabs are sloped toward the overhead door or a floor drain.
  • Exterior slabs are sloped away from the building.
  • Basement slabs are sloped toward floor drains where they are installed.
  • Equipment pads must be level.
  • Check elevation at the corners, mid-spans and edges.

Your drawings give the slope. As a guide, 1% is 10 mm per metre, about 1/8 in per foot. Example: a 6 m (20 ft) garage slab sloping 1% to the door is 60 mm (about 2 3/8 in) lower at the door end.

Pouring considerations

A 6 m × 6 m slab, 100 mm thick: 6 × 6 × 0.1 = 3.6 m³, about 4.7 yd³, before waste.

  • Place evenly so forms are not pushed out of line.
  • Screed to the form tops to hold the level.
  • Consolidate structural slabs with a vibrator or by rodding.
  • Watch the forms for movement during the pour.
  • Keep mesh or rebar at its set height.
  • Do not place concrete on frozen ground, and do not add water to the mix on site.

Common mistakes

  • Wrong elevation or slope
  • Weak staking
  • Mesh or rebar lying on the ground
  • Missing isolation joints
  • An uneven base, giving a slab of uneven thickness
  • Poor drainage planning
  • Pouring onto a wet, soft or frozen base
Pro note

Set the forms perfectly, because every error shows. Walk the pour with the slope in mind. Exterior slabs that do not drain away from the building fail early.

Weather note

Hot, windy weather dries the surface too fast and causes cracking. Cold weather slows set and risks frost damage. Rain can wash out the surface and soak the base. Plan finishing and curing around the forecast.

What the inspector looks at

Before a slab pour: base thickness and compaction, vapour barrier, insulation and reinforcement where required, forms and elevation. Book it in advance.

✅ Check yourselfTap a question
What is the minimum slab thickness in the model code, and how tall must the form board be?
At least 75 mm (3 in) exclusive of topping (9.16.4.3). The form board must be at least as tall as the slab is thick. A 38 x 89 mm (2x4) is only 89 mm (3 1/2 in) tall, so for a 100 mm (4 in) slab use a 38 x 140 mm (2x6).
A 6 m × 6 m (20 ft × 20 ft) slab is 100 mm (4 in) thick. How much concrete before waste?
6 × 6 × 0.1 = 3.6 m³, about 4.7 yd³. Add an allowance as on the Concrete Mathematics page.
Joints should be spaced at 24 to 36 times the slab thickness. What spacing is that for a 100 mm slab, and how would you lay out a 6 m × 6 m slab?
24 × 100 = 2.4 m and 36 × 100 = 3.6 m (8 to 12 ft). Cut joints at 3 m (10 ft) both ways, which makes four 3 m × 3 m panels. Keep panels square, with length no more than 1.5 times width.
A 6 m (20 ft) garage slab must slope 1% toward the door. How much lower is the door end?
1% of 6,000 mm = 60 mm, about 2 3/8 in. 1% is 10 mm per metre, about 1/8 in per foot. Your drawings give the actual slope.
Why must mesh or rebar sit on chairs, not on the base?
Steel lying on the ground does nothing, and mesh walked into the base does nothing either. It has to sit up in the slab at the height the drawings give.
Can you pour on a wet, soft or frozen base?
No. Fix soft spots with compacted granular fill, drain the base, and never place concrete on frozen ground. It thaws and settles.
🧰 Gear for this stepMust-haveRent itNice to have
  • Must-haveLayout and measuring:
  • Nice to haveLayout by laser: a rotary laser with a receiver
  • Must-haveForms:
  • Must-haveBase preparation by hand:
  • Rent itBase preparation by machine: a plate compactor
  • Must-haveBase materials:
  • Must-haveReinforcement:
  • Must-haveJoints:
  • Must-havePouring and screeding:
  • Must-haveInsulation where drawn:
  • Must-havePPE:
👷 Who can do thisTap your level
Home DIY
A capable owner can form and pour a small slab, walk or equipment pad to a simple plan, if there is no structural element. Do not pour a slab that carries walls, a thickened-edge footing or anything engineered without drawings, and hire a pro where a permit or inspection is needed. Do not put electrical, gas or plumbing under the slab yourself.
Laborer or helper
Strip, haul, rake and carry under direction, and stay out of the way of the screed and the truck. Keep chairs and tools from tearing the vapour barrier where one is placed. Tell your lead if the base is wet, soft or pumping, or if a form moves.
1st-year apprentice
You can strip topsoil, compact the base, set forms to grade, place chairs and mesh, and screed under supervision. Learn to read grades and use the laser first.
Apprentice, 2nd to 4th year
Help set forms, place chairs and check grades with the laser while a journeyperson watches. Learn to check base thickness, slab thickness and slope before the pour. You do not sign off on the base. Report any soft spots that will not compact.
Journeyperson
You own base preparation, form elevation and slope, reinforcement position, joint layout and the readiness check before the pour. Stop-work triggers: soft spots that will not compact, a wet or frozen base, or a grade the drawings do not cover (call the engineer).
Lead hand or foreman
Walk the whole base, vapour barrier, reinforcement and forms before the truck is called. Hold the pour on soft spots, a wet or frozen base, or any grade the drawings do not cover. Coordinate with the trades working under the slab. Call the engineer for anything outside the drawings.
Contractor or business owner
Price base material, forms, labour, finishing and curing. Document the base, insulation and vapour barrier with photos before the pour, and keep the inspection record. Ask your lawyer or insurer who carries the cost of a slab that cracks, ponds or has to be replaced.
Starting a new business
Learn what the drawings and the code require under a slab before you quote. Price base, barrier, insulation, joints and curing, and ask your building department when inspection is needed. Subcontract structural slabs until you have the experience, and ask your insurer what warranty claims on slabs are covered.
By Province:

Slab thickness, base, vapour barrier and concrete strength for houses come from NBC Part 9 (Sections 9.16 and 9.3) as each province adopts it, and from CSA A23.1 for exterior and garage concrete. Confirm the clause and your provincial edition.

  • BC: BC Building Code. AB, SK, MB, ON, QC: each adopts the model code with its own edition and amendments. Check yours with the local authority.
  • NB, NS, PE: footings and foundations are inspected before backfilling. NL: municipal rules apply to houses.
  • YT: Whitehorse requires a foundation and under-slab inspection before backfill. NWT, NU: confirm locally.

See Permits and Approvals for the inspection stops, and Canada by Province for the comparison.

Sources:

Last reviewed October 2026. General information, not engineering or legal advice.