Footing Forms

Written for Canada. Plans are metric, but many crews and suppliers work in feet and inches, so this site gives both: millimetres and metres, with feet and inches beside them. Codes are the National Building Code of Canada 2020 (NBC 2020) Part 9 as your province adopts it. A number marked Confirm has not been checked against every province, so check it with your own authority before you act on it.

Reviewed by a working tradesman with 17+ years in the field.

Some links on this site are affiliate links. If you buy through them we may earn a commission at no extra cost to you. Affiliate disclosure

The forms that set a footing's width, thickness, level and position, built right before the concrete goes in.

I am a:

Tap your level and the boxes below open to the advice for you. Remembered on this device.

What it isThe forms that decide a footing's width, thickness, level and position.
Why it mattersOnce the concrete is in, none of those can change. 25 mm (1 in) low shows later as a crooked wall.
Where the numbers come fromThe drawings first. For a plain house, Part 9 of the code as your province adopts it.
The baseUndisturbed soil or compacted granular fill, clean, unfrozen and dry.

By the end you can

  • Tell strip footings, pads, grade beams and thickened edges apart.
  • Find the footing width and thickness for a plain house, and know when the drawings override it.
  • Build, brace and check a form for width, level and square.
  • Prepare the base, and say what stops a pour.
  • Know what the inspector checks before the concrete goes in.
Stop and read

Footing forms are built inside an excavation. If the hole is deeper than 1.2 m (4 ft), the trench rules apply to you while you set forms and rebar (see Trench Safety; the legal trigger is 1.5 m in Alberta and Manitoba). Do not work under an unsupported wall to "just finish the corner".

The big idea

A footing spreads the weight of the building over the soil. The forms decide its width, thickness, level and position, and once the concrete is in, none of those can be changed. A footing 50 mm (2 in) off centre, or 25 mm (1 in) low, shows up later as a crooked wall or a stepped slab. Take the time here.

Types of footings

  • Strip footings: continuous footings under foundation walls.
  • Pad footings: isolated footings under columns, posts or point loads.
  • Grade beams: reinforced beams spanning between pads or piles. These are engineered.
  • Thickened slab edges: slab edges or interior zones thickened to carry a load.

Check the drawings before you cut a board

For anything larger or unusual, footing size comes from the structural drawings. For a typical house, it comes from Part 9 of the building code in your province (based on the NBC). Either way, write the numbers on your layout and on the form itself so the next person does not guess.

The model code, Part 9, Section 9.15.3, says:

  • Footings rest on undisturbed soil, rock or compacted granular fill (9.15.3.2).
Floors supportedExterior wall stripInterior wall stripColumn footing area (columns 3 m / 10 ft apart)
1250 mm (9 7/8 in)200 mm (7 7/8 in)0.4 m² (4.3 ft²)
2350 mm (13 3/4 in)350 mm (13 3/4 in)0.75 m² (8.1 ft²)
3450 mm (17 3/4 in)500 mm (19 5/8 in)1.0 m² (10.8 ft²)
  • Thickness is at least the greater of 100 mm (4 in) and the footing's projection beyond the wall (9.15.3.8).
  • Steps: the rise between level parts is no more than 600 mm (23 5/8 in), and the run between risers is at least 600 mm (9.15.3.9).
  • Wet or loose ground: on gravel, sand or silt with the water table below the footing width, walls need twice the width and columns twice the area (9.15.3.4(3)).
  • Extra width is added for masonry veneer, masonry walls and flat insulating concrete form walls (9.15.3.5).
  • Depth below finished ground follows Table 9.12.2.2. For clay or unclassified soil it is generally 1.2 m (3 ft 11 in); other soils depend on frost and heating (9.12.2.2).

Working it out

Wall footing. A two-storey exterior wall, 200 mm thick, on a 350 mm footing: projection = (350 − 200) ÷ 2 = 75 mm (3 in), so the minimum thickness is the greater of 100 mm and 75 mm, which is 100 mm (4 in). The drawings usually call for more than the minimum.

Column pad. A one-storey column at 3 m spacing needs 0.4 m², so a square pad is √0.4 = 0.632 m (24 7/8 in) a side. Two floors at 0.75 m² need 0.866 m (34 in).

Confirm

These numbers are from the model code as printed in the Vancouver Building Bylaw 2014. Check the article numbers and the edition your province adopts, and ask your building department about frost depth, which it has the final say on.

Footing layout

  • Mark footing width and the wall centreline. The wall sits on the footing's centre unless the drawings say otherwise.
  • Mark column centrelines and pad locations from the gridlines.
  • Mark step-downs and elevation changes before forming starts.
  • Plan anchor bolt and dowel positions so form hardware and rebar do not clash.
  • Check the diagonals. Equal diagonals mean a square building (see Elevation and Layout).

Forming materials

A cutaway of a footing trench with form boards on both sides held by stakes and kickers, a spreader across the top, rebar on chairs, and a dashed outline of the wall that goes on later, centred on the footing.
A formed strip footing. Form boards on both sides, held by stakes and kickers. A spreader keeps the width exact. Rebar sits on chairs with cover to the soil. The footing bears on undisturbed soil or compacted granular fill, and the wall is centred on it. Not to scale.
  • Lumber forms: 38 x 235 mm (2x10) or 38 x 286 mm (2x12) boards, 38 x 89 mm (2x4) stakes, spreaders and kickers. Use straight, sound lumber, without large knots or splits at the edge.
  • Panel systems: steel or aluminum panels with corner pieces and strongbacks. Faster on long runs.
  • Hybrid: panels for straight runs, lumber for steps and odd corners.

Building the forms

  1. Snap lines. Mark footing edges and the centreline on the prepared base.
  2. Set corner stakes. Establish the corners, then pull string lines to check straightness.
  3. Set the form boards. To the snapped line and the elevation. The top of the board is the top of the footing.
  4. Fasten to the stakes. Screws or nails, driven so the board is not pushed out of line.
  5. Add spreaders. Hold the width along the full run, not just at the corners.
  6. Brace with kickers. Wet concrete is heavy and pushes outward. Brace for that, not for the empty form.
  7. Check the elevation. Laser or level at corners, mid-spans and steps, not just the corners.
  8. Place the rebar. On chairs, with the cover the drawings call for (see Rebar Placement).
  9. Walk it. Width, depth, elevation, rebar, bracing and a clean base. Fix problems now.

Footing base preparation

The soil under a footing matters as much as the concrete. Concrete cannot make up for a soft base.

  • Strip topsoil, roots and organic material. The bottom of every excavation must be free of organic material (9.12.1.1).
  • Remove loose soil and soft spots and replace them with compacted granular material, not loose dirt.
  • Level the base so the footing thickness is even.
  • Excavations must be kept free of standing water (9.12.1.2), and kept from freezing for the whole construction period (9.12.1.3). Never pour into mud, onto ice or onto frozen ground. It thaws and settles.
What the inspector looks at

The footing and form inspection happens before concrete is placed. Expect them to check width and thickness, depth to undisturbed soil, a clean base, the forms and elevation, and the rebar if it is required. Book it ahead and leave time to fix what they find. Your municipality's sequence and notice period are the ones that count.

Pouring considerations

  • Place concrete evenly along the run so one side is not pushed out of line.
  • Consolidate with a vibrator or by rodding to remove air pockets.
  • Watch forms and stakes during the pour and correct movement immediately.
  • Plug leaks before you lose a lot of concrete.
  • Keep rebar on its chairs. Do not let it get walked into the soil.

For commercial and civil footings, use heavier forms and bracing, follow the engineered formwork drawings, use anchor bolt templates for columns and steel, and coordinate critical positions with the surveyor.

Common mistakes

  • Width or depth different from the drawings
  • Wrong elevation, which then shows up in wall or slab heights
  • Not enough bracing, leading to a blowout
  • Rebar too low, touching the soil
  • Missing dowels or wrong spacing
  • Water under the footing reducing bearing
  • Pouring on frozen or soft ground
Pro note

Check width, depth and elevation before the rebar goes in. After that every change is slow. Use more kickers than you think you need. On engineered jobs, verify column centrelines with a laser or total station before the pour.

Weather note

Wet soil lets stakes shift. Cold stiffens lumber and makes nails brittle, and frost can get under forms. Hot, dry weather pulls moisture out of the base and leaves voids under boards. Adjust stake depth, bracing and checks to the conditions.

Code note

Footings must bear on undisturbed soil or compacted granular fill, below the depth the code and your municipality require, and be sized to the drawings or the Part 9 table. Footing concrete in the model code is a minimum 15 MPa at 28 days with a maximum water to cementing ratio of 0.70 (9.3.1; see Concrete Mathematics). They are inspected before the concrete is placed.

✅ Check yourselfTap a question
A one-storey house has an exterior strip footing. What is the minimum width in the model code table, in mm and inches?
250 mm, which is about 9 7/8 in. Two floors need 350 mm (13 3/4 in) and three floors 450 mm (17 3/4 in). The drawings can ask for more.
A two-storey exterior wall is 200 mm (7 7/8 in) thick and sits on a 350 mm (13 3/4 in) footing. What is the minimum thickness?
The projection each side is (350 − 200) ÷ 2 = 75 mm (3 in). Thickness must be at least the greater of 100 mm (4 in) and the projection, so 100 mm. The drawings usually call for more.
The grade drops 1.0 m (3 ft 3 in) along a footing run. How many steps do you need at minimum, and how far apart?
Each rise may not exceed 600 mm (23 5/8 in). 1,000 ÷ 600 = 1.67, so 2 steps, for example 500 mm each. Each run between risers must be at least 600 mm (23 5/8 in).
A column footing under a 1-storey load at 3 m spacing needs 0.4 m². What square side is that?
√0.4 = 0.632 m, so about 632 mm (24 7/8 in) square. For 2 floors, 0.75 m² gives 0.866 m (34 in).
The footing bottom is soft and wet after rain. May you form on it?
No. Remove soft spots and replace them with compacted granular fill, pump out the water and keep it out. Concrete cannot make up for a soft base.
Why brace the form for the wet concrete instead of the empty form?
Wet concrete pushes outward and is heavy. An empty form only has to stand. Use more kickers than you think you need.
🧰 Gear for this stepMust-haveRent itNice to have
  • Must-haveLayout and measuring:
  • Must-haveForming:
  • Must-haveCutting and fastening:
  • Must-haveBase prep by hand:
  • Rent itBase prep by machine:
  • Must-haveRebar and finishing:
  • Must-havePPE:
👷 Who can do thisTap your level
Home DIY
You can form a small pad or deck footing from a drawing or permit set. Do not work in a hole over 1.2 m (4 ft), and do not form footings for a house or garage without a permit and the code or engineer's sizes. Hire a pro for engineered footings and grade beams.
Laborer or helper
Cut boards, drive stakes and carry material under direction. Never enter a hole over 1.2 m (4 ft) that is not protected, and never decide a hole is safe. Do not stand under or beside an unsupported wall. Tell your lead if the bottom looks wet or soft.
1st-year apprentice
You can snap lines, set stakes, build and brace form boards, and check elevations under supervision. Learn to read footing size from the drawings first, and to brace for wet concrete, not an empty form.
Apprentice, 2nd to 4th year
Set form boards and stakes from a marked line, then check width, depth and elevation with the drawings in hand. Brace for wet concrete, not an empty form. You do not accept the base. Tell your journeyperson about any soft or wet spot before forming.
Journeyperson
You own width, depth, elevation, bracing and the base condition, and you book the inspection. Stop-work triggers: soft spots, wet or frozen ground, or soil that does not match the drawings. Stop and let the engineer see it before you form or pour.
Lead hand or foreman
Check size, elevation, bracing and base against the drawings before you book the inspection. Hold forming for soft, wet or frozen ground and let the engineer see it. Keep the crew out of any hole over 1.2 m (4 ft) unless it is protected. Do not override the engineer.
Contractor or business owner
Price form material, bracing and re-work, and book the footing inspection before the pour. Keep photos and survey checks. Ask your lawyer or insurer who carries the liability for a footing built to the wrong size, depth or bearing.
Starting a new business
Before your first footing job, learn the code and drawing requirements for footing size and bearing, and ask your building department when the inspection must happen. Price re-work and inspection waits. Subcontract engineered footings to an experienced crew and keep the engineer's letter.
By Province:

Footing size, depth and concrete strength for houses come from Part 9 as each province adopts it, or from the engineer's drawings. Confirm the clause and your provincial edition.

  • BC: BC Building Code. Vancouver inspects after the formwork and before the pour.
  • SK: Saskatoon has a footing inspection after the pour and stripping. Regina has a foundation inspection after rebar and before the pour.
  • ON: notify the chief building official when ready to construct footings, and before backfilling.
  • NB, NS, PE: footings and foundations are inspected before backfilling. NL: municipal rules apply to houses.
  • YT: Whitehorse requires a foundation inspection before backfill.
  • AB, MB, QC, NWT, NU: ask the local authority for the footing depth, frost protection and inspection requirement.

See Permits and Approvals for the inspection stops, and Canada by Province for the comparison.

Sources:

Last reviewed October 2026. General information, not engineering or legal advice.