Permits and Approvals
Reviewed by a working tradesman with 17+ years in the field.
Some links on this site are affiliate links. If you buy through them we may earn a commission at no extra cost to you. Affiliate disclosure
What to ask, what to submit and which inspections to book, before you price the job or put a shovel in the ground.
Tap your level and the boxes below open to the advice for you. Remembered on this device.
By the end you can
- Say who issues the permit for your job and what to ask them.
- Tell structural work, which needs a permit, from flatwork, which often does not.
- List the documents an application usually asks for.
- Book the inspection stops in the right order and know what fails them.
- Book a utility locate and know which buried lines it will not find.
Do not pour, backfill or cover any work that is waiting on an inspection. Do not start digging until the locate is back and the lines are marked. An inspector cannot inspect a trench that is not safe to enter, and nobody goes into a trench deeper than 1.2 m (4 ft) unless it is protected.
The big idea
A permit is how your work gets checked against the building code, zoning and safety rules. Unpermitted structural work can mean a stop-work order, tear-out, trouble with insurance and problems when you sell. The cheapest tool in this whole stage is a five-minute call.
The National Building Code of Canada is a model code. It has no force until a province or territory adopts it, and many adopt it with changes. The permit itself usually comes from the local authority: a city, town, district or municipality in BC, AB, SK, ON and QC. In PEI the province issues permits outside Charlottetown, Stratford, Summerside and St. Felix. In Nunavut permits go through the Office of the Chief Building Official. Elsewhere, ask your municipality who issues it.
Who issues what
Using BC as the example. In other provinces the same jobs are done by different bodies, so ask your local building department and provincial regulator.
| Approval | Who | Note |
|---|---|---|
| Building permit | Local government building department | Under the BC Building Code and its own building bylaw. |
| Zoning, setbacks, height, coverage | Same local government, under its zoning bylaw | A permit can be refused over setbacks even when the structure is perfect. |
| Electrical, gas, plumbing | Provincial regulator and/or local building department | Ask which one at the counter. |
| New home by an owner-builder | BC Housing (Homeowner Protection Act) | Exam, then an Owner Builder Authorization. |
| Near water, farmland or First Nations land | Provincial, federal or First Nations authorities | See Other approvals below. |
If you build your own home
The rules differ a lot by province. These are the ones we checked against the official pages.
- BC. You must pass an exam and get an Owner Builder Authorization from BC Housing before you build. If you sell within 10 years of construction you stay personally liable for defects and must give buyers a disclosure notice. In most cases you cannot list the home until it is finished and you have lived in it for at least a year.
- AB. Owner Builder Authorization under the New Home Buyer Protection Act, for a single-family site-built home for personal use. You must be a registered owner, plan to keep the home 10 years, and manage the construction yourself. The fee is $95 with warranty or $750 without. Without warranty you cannot sell or offer to sell during the 10 years, and a caveat goes on the title (authorizations issued from 1 December 2025). The authorization lets you get building permits without a builder licence. Lenders may require warranty, so ask yours first.
- ON. Get a Tarion Letter of Confirmation before you apply for a permit. Owner-built homes carry no statutory warranty.
- SK, MB, QC and others. See the By province table. Where it says Confirm, we have not checked the source yet.
Do I need a permit?
There is no national rule that says "under X it needs no permit". Each authority sets its own thresholds. Most departments think about the work in these groups.
| Work | Typical result |
|---|---|
| Footings, foundation walls, grade beams. Slabs that carry walls or posts. Any slab attached to a building. | Building permit and a series of inspections. Treat as always required unless the department tells you otherwise in writing. |
| Full foundations, basement excavation, frost walls, sealed crawl spaces, engineered slabs. | Building permit, several inspections, often engineer's drawings or a geotechnical report. |
| Retaining walls, especially near a property line, road, slope or building. | Permit and an engineer's design once the wall passes a certain height or carries a surcharge. The height varies by municipality. |
| Walkways, patios and pads that do not support a structure. | Often no building permit, but not always. Drainage changes, driveway approaches and work in a utility right-of-way can need their own approval. |
| Excavation, grading, utility trenching, clearing, large fill or soil movement. | Depends on the municipality. Many have soil-removal, fill or tree bylaws, erosion control rules and separate permits for driveway crossings. |
- Anything attached to a building or carrying new load
- Changing drainage or sending water onto a neighbour or the road
- Digging near utilities, a property line or an existing structure
- New plumbing, gas or electrical
- New driveway access, culverts or work in the road allowance
- Building near a stream, a steep slope or the setback line
The steps
- Call the building department for the address. Say exactly what you plan to build. Ask what permits, drawings, reports and inspections it needs.
- Get the application checklist. Departments differ on what they check at the counter, such as owner-builder authorization or warranty proof.
- Assemble the documents. See the list below. Order a survey or geotechnical report early, since they take weeks.
- Submit, pay and wait. Ask how long review takes at the moment and build it into your schedule.
- Post the permit and keep the approved drawings on site. Most authorities want both available to the inspector, and many want the permit card visible.
- Book each inspection with notice. The stops and the notice period are on your permit. Do not pour or cover until the stop has passed.
- Photograph everything. The permit, the drawing revision stamp and every passed inspection card, dated.
Documents you may be asked for
- Approved construction drawings: plans, sections, details
- A site plan, often based on a survey by a licensed land surveyor
- Structural drawings and an engineer's stamp where required
- A geotechnical report if the soil, slope or water table calls for one
- Drainage and erosion and sediment control plans
- Energy and envelope compliance information for new buildings
- Letters of Assurance where the building requires them
Letters of Assurance (BC)
In BC these signed documents are how architects and engineers accept responsibility for design and field review. Ask the counter which Part 9 buildings need them and whether your geotechnical engineer has to sign one. Other provinces use their own sign-off systems. In Ontario, for example, designers need a BCIN.
| Schedule | What it does | When |
|---|---|---|
| A | Confirms a Coordinating Registered Professional has been hired | With the permit application |
| B | A Registered Professional of Record takes responsibility for a component and its field reviews | Before that component is built |
| C-A, C-B | Confirm the professionals finished their duties | After completion, before occupancy or final inspection |
Inspection stops for a foundation
Where we verified the stops (examples in BC, SK, ON, NB, NS, PE and Whitehorse), foundation work is inspected before it is covered. Your permit has the real list. A typical sequence:
- Excavation and bearing soil Sometimes with the geotechnical engineer's field review.
- Footing forms and reinforcement Before any concrete goes in.
- Foundation wall forms and reinforcement If the walls are poured.
- Damp-proofing and perimeter drain tile Before backfilling.
- Under-slab Gravel, vapour barrier, insulation and any under-slab plumbing, before the slab is poured.
- Backfill or grading Some departments inspect this too.
Inspectors fail footings for plain things: standing water in the bottom, disturbed or frozen soil, forms off line or out of level, rebar not on chairs or at the wrong cover, and the drawings not on site. Book with notice, have the approved drawings there, and make the site safe to enter.
Utility locates
Contact your province's one-call service before you dig. Locates are free. Private lines are not mapped by the service. The numbers below were checked against official or utility pages in October 2026, but take the number from the current official page before you call.
| Province | Service | Notice | Note |
|---|---|---|---|
| BC | BC 1 Call, bc1c.ca, 1-800-474-6886 (*6886 from a cell) | 3 full business days | BC Energy Safety (Technical Safety BC) calls it a free service and recommends it before any digging. Check whether your municipality or utility makes it a condition of your permit. |
| AB | Alberta One-Call, 1-800-242-3447, web requests 24/7 | 3 full business days | Utility Safety Partners says members need a minimum of 3 full business days. Private lines are not located (see below). |
| SK | Sask 1st Call, 1-306-777-9507 (office line) | 2 full working days (SaskEnergy). The City of Regina asks for 3 business days for its own lines. | Allow 3. Confirm the current request number and web portal with Sask 1st Call. |
| MB | Click Before You Dig Manitoba, clickbeforeyoudigmb.com, 1-800-940-3447 | They contact you within 3 business days with a locate date | Manitoba Hydro says homeowners need to use it before digging deeper than 15 cm (6 in). The locate is valid for 14 days; if work has not started, have the lines re-marked. |
| ON | Ontario One Call (now Ontario Dig Authority) | Confirm (5 business days was the figure on our old page) | Ontario has a law on this (Underground Infrastructure Notification System Act, 2012). Confirm the lead time and your duties with Ontario One Call before you dig. |
| QC | Info-Excavation, info-ex.com | 4 working days | The RBQ calls the request essential and lists it as a contractor responsibility. A request stays valid up to the work end date you enter, for a maximum of 180 days. |
| NS, NB, PE, NL | Confirm with your utilities | Confirm | Sources for these provinces conflict or are missing, so we are not printing a number we cannot stand behind. |
| YT, NT, NU | No territory-wide one-call that we could confirm | Confirm | Call the power, telephone and gas utilities for your town directly. |
Private lines: sprinklers and irrigation, a line from the house to a shed or garage, septic tanks, tile beds, well pipes, and the water and sewer from the property line to your house. Find those yourself or hire a private locator. Hand tools can still damage a line, so follow the hand-expose zones on the locate report before any machine digs.
Other approvals people forget
- Archaeology and heritage. If you find bone, shell midden, stone tools or other unusual material, stop work in the area, leave everything in place and report it. Every province has a process, and on or near First Nations land local First Nations may also need to be consulted. In BC the Heritage Conservation Act protects archaeological sites on private land too; contact the Archaeology Branch.
- Streams, wetlands and riparian areas. Provincial and federal rules and local setbacks can restrict work near water. Ask before you clear or dig.
- Agricultural Land Reserve (BC). Extra rules on soil removal, fill and non-farm use.
- Contaminated or imported soil. Moving soil on or off site can be regulated.
- Worker safety. Your provincial OHS regulator sets rules for workers on site, whether or not a permit is needed. Who counts as the responsible constructor differs by province. In NB and NS the owner is deemed the constructor where no one else controls the work. In Ontario the OHSA does not cover an owner's own work on a private residence, but an owner who hires several contractors with no general contractor is likely the constructor.
- Hiring help and workers' compensation. In BC a homeowner must register with WorkSafeBC if a one-time project reaches 24 or more total hours across all workers, or ongoing work runs 8 or more hours a week. In NB a homeowner generally cannot register unless they are an employer. In NL a homeowner employing people at a private residence is not required to register. Ask your board before you hire anyone.
Riparian setback distances (30 m is commonly quoted) depend on the stream and the local bylaw and have not been checked here. Heritage phone numbers and the AB and MB trench-depth rules are being verified as those pages are rebuilt.
Common mistakes
- Pricing before asking. The department's answer changes the job. Call first.
- Booking concrete before the inspection. Inspectors have their own schedule. Never pour on a stop that has not passed.
- Trusting the locate for private lines. It does not find them.
- Drawings not on site. An easy fail, and it costs a day.
- Treating a field change as minor. Send it to the designer or building department in writing.
The permit costs money and the job is small. Can you skip it if the slab is only 10 m²?
What is the difference between a building permit and a utility locate?
The footing forms are done and the inspector cannot come until Thursday. The truck is booked for Wednesday. What do you do?
Which lines will a one-call locate not mark?
You find a bone and a flaked stone tool while digging. What now?
Who is responsible for site safety on an owner-built job?
- Must-havePaper and records:
- Must-haveCamera:
- Must-haveTapes:
- Must-haveMarking paint or stakes to show the footprint to the inspector
- Must-haveHard hat (CSA Z94.1), safety glasses (CSA Z94.3) and green-triangle footwear (CSA Z195) for any inspection visit
- Rent itLaser or builder's level with a grade rod, so you can show the inspector elevations
- Nice to haveA weatherproof permit box or board to post the permit and drawings
Home DIY
Laborer or helper
1st-year apprentice
Apprentice, 2nd to 4th year
Journeyperson
Lead hand or foreman
Contractor or business owner
Starting a new business
NBC 2020 Part 9 sets the model rules, but who issues the permit, who may owner-build and when inspections happen are provincial and municipal.
- BCFSA, Homeowner Protection Act information (owner builder exam, 10-year rule, disclosure notice, one-year occupancy)
- Government of Alberta, Owner Builder Authorization
- Technical Safety BC, Call Before You Dig
- Utility Safety Partners, Damage Prevention Process, Homeowners Edition v1.4
- Manitoba Hydro, Click Before You Dig
- City of Regina, Underground line locates
- SaskEnergy, Safe Digging Month notice (two working days)
- Régie du bâtiment du Québec, Excavation work
- National Building Code of Canada 2020, Part 9; provincial building acts and codes. Ontario Tarion and Ontario One Call details are still to be verified against the primary pages.
Last reviewed October 2026. General information, not engineering or legal advice.