Written for Canada. Plans are metric, but many crews and suppliers work in feet and inches, so this site gives both: millimetres and metres, with feet and inches beside them. Codes are the National Building Code of Canada 2020 (NBC 2020) Part 9 as your province adopts it. A number marked Confirm has not been checked against every province, so check it with your own authority before you act on it.

Reviewed by a working tradesman with 17+ years in the field.

Some links on this site are affiliate links. If you buy through them we may earn a commission at no extra cost to you. Affiliate disclosure

The perimeter drain collects water at the footing and sends it somewhere safe. Height, stone and outlet decide whether it works.

I am a:

Tap your level and the boxes below open to the advice for you. Remembered on this device.

What it isThe perforated pipe at the footing that collects water and sends it somewhere safe.
Your jobLay it beside the footing on sound soil, with its top below the slab, in clean stone wrapped in fabric, running to a proper outlet.
The hard ruleAt least 100 mm (4 in) pipe, top below the underside of the slab, and 150 mm (6 in) of clean stone on top and sides.
The checkPipe, stone, fabric and outlet checked and photographed around the whole house before backfill.

By the end you can

  • Place a drain at the right height beside the footing.
  • Build the stone and fabric envelope around it.
  • Choose a legal outlet and say when a sump is needed.
  • Check the system before it is covered.
Stop and read

You are working in a hole beside a tall wall. Treat any excavation 1.2 m (4 ft) or deeper as a trench, and follow the Trench Safety page and your provincial OHS regulator. Keep excavations and heavy equipment clear of the footing, because digging below or too close to it can undermine it. Stop if water is running into the trench or the bottom is soft.

The big idea

The perimeter drain is the part of the system that actually removes water. It collects water at the footing and sends it somewhere it can safely go. If it is too high, laid badly, or set in dirty stone, water finds its way into the house.

What the code says

From Part 9, Section 9.14, as printed in the Vancouver Building Bylaw 2014:

  • The bottom of every exterior foundation wall is drained by drain tile or pipe around the foundation, or by a gravel or crushed rock layer, unless it can be shown to be unnecessary (9.14.2.1).
  • Materials: the listed standards include perforated clay and concrete tile, CAN/CSA-B182.1 plastic drain and sewer pipe, and BNQ 3624-115 flexible polyethylene drainage pipe (9.14.3.1).
  • The pipe is at least 100 mm (4 in) in diameter (9.14.3.2).
  • It sits on undisturbed or well-compacted soil, with its top below the bottom of the floor slab (9.14.3.3).
  • Butt joints are laid with 6 to 10 mm (1/4 to 3/8 in) open joints, with the top half of the joint covered by sheathing paper, 0.10 mm polyethylene, or No. 15 felt.
  • The top and sides are covered with at least 150 mm (6 in) of crushed stone or other coarse clean granular material, with no more than 10 percent passing a 4 mm sieve.

The text I read gives no slope, no cleanout provisions, and no bedding under the pipe beyond sound soil. Your province's edition may add them. Confirm with your building department and the designer.

Pipe types

  • Rigid perforated plastic: holds its fall and resists crushing. A trade guide calls rigid pipe crush-resistant and says its holes are less likely to clog than the narrow slots in coiled pipe.
  • Flexible corrugated pipe: allowed if it meets the listed standard (BNQ 3624-115), but it can sag and crush, and rock can crush it during backfill. A trade guide says not to pitch flexible pipe, and to lay it on the footing shelf.
  • Whatever you use must meet a standard your code lists. Confirm what your province accepts.

Where it goes and how it falls

  • Beside the footing, on undisturbed or well-compacted soil, never on loose fill. Do not put it halfway up the wall or above the footing.
  • The top of the pipe is below the underside of the floor slab. A trade guide says perimeter drain pipe should never be above the slab surface.
  • Holes down, onto a bed of stone, is the common layout in the trade guides, and the drawing on the Membranes page shows it. One building-science article says a drain with the holes up still works, just less well. The code text I read is silent on this.
  • Fall: the code text I read gives none. One trade guide sets rigid tile straight and level, or with a slight pitch toward the outlet. A building-science article says the perforated pipe can be level, and the solid outlet pipe should fall at least 1/4 in per foot (about 2 percent).
  • Check the grade with a laser or level while you lay it, not after. No dips, kinks or high spots that hold water.

Example. A solid outlet pipe 20 m (65 ft 7 in) long at 1/4 in per foot drops 20 × 0.0208 = 0.42 m (16 1/2 in). That tells you early whether a daylight outlet is possible on the lot. The run is made up.

Stone and fabric

  • Clean crushed stone, with no more than 10 percent passing a 4 mm sieve, at least 150 mm (6 in) on the top and sides of the pipe (9.14.3.3).
  • A trade guide gives about 50 to 75 mm (2 to 3 in) of stone under the pipe. The code text I read gives no figure, so follow your drawings.
  • Wrap the stone, not the pipe, in filter fabric where fine soil could wash in. The two enemies of a footing drain, according to a building-science article, are fine silt and tree roots.
  • Backfill with coarse granular material against the wall, and cap with soil that sheds surface water.

Joints, fittings and cleanouts

  • Use proper manufactured fittings for corners and connections.
  • Cleanouts: the code text I read has none, but two trade sources say to plan them before you dig, so the drain can be cleaned later. Capped risers at corners are common. Ask your inspector what yours expects.
  • Keep downspouts off the foundation drain. A building-science article says tying them in is not uncommon and brings in debris.

Connection to the outlet

  • Foundation drains discharge to a sewer, a drainage ditch or a dry well (9.14.5.1).
  • Where gravity drainage is not practical, a sump pit and an automatic pump are required (9.14.5.2). The next pages cover sumps and discharge lines.
  • A dry well is allowed only where the groundwater is below its bottom, and it must be at least 5 m (16 ft 5 in) from the foundation (9.14.5.3).
  • A building-science article says to run to daylight rather than rely on a pump, and to add a second outlet for more than about 60 m (200 ft) of foundation.

Before backfill

  • Check the pipe level and fall around the whole building.
  • Check the stone depth and cleanliness, and the fabric.
  • Check the pipe is not crushed or kinked.
  • Check the outlet connection.
  • Take photos for your records.

Common mistakes

  • Pipe above the footing or the slab
  • Pitching flexible pipe, so it dips
  • Dirty stone
  • No filter fabric where soil could wash in
  • Pipe crushed during backfill
  • Downspouts tied into the drain
  • Blocked or missing outlet
Pro note

The drain is the most important part of the waterproofing. Spend the most time here, and photograph the pipe before it is covered.

Weather note

Rain floods the trench and washes fines into the stone. Cold stiffens plastic pipe and makes leveling harder. Wind blows soil into open stone.

What the inspector looks at

Pipe type, location and fall, stone depth and cleanliness, fabric, cleanouts, and where it discharges, before backfill.

✅ Check yourselfTap a question
A solid outlet pipe runs 20 m (65 ft 7 in) to daylight at a 1/4 in per foot fall. How far does it drop?
1/4 in per ft is about 2.1 percent, or 1 in 48. 20 m × 0.0208 = 0.42 m (16 1/2 in). That is the outlet only, and you need that much fall available on the lot.
What is the minimum pipe size and where does the top of the pipe sit, under Part 9?
At least 100 mm (4 in) in diameter, with the top of the pipe below the bottom of the floor slab (9.14.3.2 and 9.14.3.3).
What goes around the pipe?
At least 150 mm (6 in) of crushed stone or other coarse clean granular material on the top and sides, with no more than 10 percent passing a 4 mm sieve (9.14.3.3).
Does Part 9 give a minimum slope for the foundation drain?
Not in the text I read. Rigid pipe is usually laid level or with a slight pitch, and flexible pipe is not pitched. Check your province and the designer.
Where may a foundation drain discharge?
To a sewer, a drainage ditch or a dry well (9.14.5.1). Where gravity will not work, an automatic sump pump is required (9.14.5.2). A dry well is allowed only where groundwater is below its bottom, and it must be at least 5 m (16 ft 5 in) from the foundation.
Why not connect roof downspouts to the foundation drain?
Two trade sources say it is not uncommon, and that it brings in debris and overloads the drain. Run downspouts away from the house.
🧰 Gear for this stepMust-haveRent itNice to have
  • Nice to haveLayout and grade (laser): a laser level or transit with a receiver rod
  • Must-haveLayout and grade (hand tools):
  • Must-havePipe and fittings:
  • Must-haveStone and fabric:
  • Must-haveDigging and placing:
  • Must-haveCutting: a hand saw or pipe cutter for plastic pipe
  • Must-haveRecords: a camera or phone for photos of the pipe, stone and fabric before backfill
  • Must-havePPE: hard hat (CSA Z94.1), eye protection (CSA Z94.3), green-triangle boots (CSA Z195), gloves, and hearing protection (CSA Z94.2) when machines are running near the hole
👷 Who can do thisTap your level
Home DIY
A capable owner can lay drain pipe and stone in an already-open trench no deeper than 1.2 m (4 ft) that a pro has dug and, where needed, shored. Do not dig beside an existing footing or foundation yourself, and do not judge sloping or shoring yourself. Hire a pro for deep basements, high water tables, or where the discharge needs a plumbing permit.
Laborer or helper
Carry stone, pass pipe and keep tools clear while a qualified person directs the work. Never enter an unprotected trench, and never decide that a trench is safe. Speak up and stop if water is running in or the wall looks wrong.
1st-year apprentice
Under supervision, set the pipe to grade, place stone and fabric, and check the fall with a laser. Learn first why pipe height, slope and clean stone matter, and the excavation rules for your province.
Apprentice, 2nd to 4th year
Place pipe and stone and check the fall with a laser under the journeyperson. Stay out of any trench not sloped or shored by a qualified person. Learn what a soft bottom and seeping water look like, and report both at once.
Journeyperson
You own the pipe location, fall, stone envelope and discharge connection, and the inspection before backfill. Stop-work triggers: stop and call the engineer if the trench bottom is soft or running with water, the pipe cannot hold a continuous fall to the discharge, or the footing is exposed or undermined.
Lead hand or foreman
Hold the stop-work triggers: stop and call the engineer if the trench bottom is soft or running with water, or the footing is exposed or undermined. Check the fall to the discharge before cover. Confirm with your provincial OHS regulator who must inspect the excavation before anyone enters.
Contractor or business owner
Price the drain, stone, discharge and a sump if gravity will not work. Book the pre-backfill inspection and keep photos. Include excavation safety, locates where required, and insurance. A drain that fails after backfill is expensive to reopen, so check before cover.
Starting a new business
Before your first drain job, learn the excavation rules with your provincial OHS regulator, and who inspects before backfill with your building department. Keep photos of every drain. Confirm liability with your insurer and lawyer.
By Province:

The technique is the same across Canada. What changes is the code edition, the accepted pipe standards, the slope and cleanout rules, and who inspects before backfill. I read Section 9.14 in the Vancouver Building Bylaw 2014, which may not match your province's current edition. Confirm the clauses with your local building department.

See Canada by Province for the full comparison.

Sources:
  • Vancouver Building Bylaw 2014, Division B, Section 9.14 (9.14.2 to 9.14.5; municipal reprint, edition may be older than yours)
  • Green Building Advisor, Foundation Drains (2022, secondary, US: level perforated pipe, 1/4 in per foot outlet, daylight outlet, silt and roots)
  • JLC Field Guide: Drainage (2023, secondary, US: holes down, pipe not above slab, do not pitch flexible tile, plan cleanouts)
  • The US guides cite US codes and practice, so treat their numbers as practice, not Canadian code. Stone depth under the pipe, slope and cleanouts need your own province's edition. Fall arithmetic is calculated and re-checked.

Last reviewed October 2026. General information, not engineering or legal advice.