Rebar Placement

Written for Canada. Plans are metric, but many crews and suppliers work in feet and inches, so this site gives both: millimetres and metres, with feet and inches beside them. Codes are the National Building Code of Canada 2020 (NBC 2020) Part 9 as your province adopts it. A number marked Confirm has not been checked against every province, so check it with your own authority before you act on it.

Reviewed by a working tradesman with 17+ years in the field.

Some links on this site are affiliate links. If you buy through them we may earn a commission at no extra cost to you. Affiliate disclosure

Putting steel bars in the right size, place, length and cover before the concrete hides them.

I am a:

Tap your level and the boxes below open to the advice for you. Remembered on this device.

What it isPutting steel bars in the right size, place, length and cover before the concrete hides them.
Why it mattersConcrete is strong in compression and weak in tension. Rebar takes the pull.
The hard ruleNever change a bar size, spacing or grade without the engineer.
The hazardExposed vertical bar ends can impale. Cap them.

By the end you can

  • Read a Canadian bar size (10M, 15M, 20M, 25M) and know its diameter and weight.
  • Explain cover and why steel sits on supports, not on the ground.
  • Work out bar counts and weights from spacing and length.
  • Place, splice and tie bars for footings, walls, slabs, stairs and retaining walls.
  • Check the steel before the inspector does.
Stop and read

Exposed rebar ends are an impalement hazard, and a fall onto vertical bars can kill. Cap or guard vertical bar ends where people work above or beside them, and check your provincial OHS regulator for the rule. Brace tall mats and cages so they cannot topple, and use proper lifting gear, gloves and eye protection when cutting and bending steel.

The big idea

Concrete is strong when squeezed and weak when pulled. Rebar takes the pull. It only works if it is in the right place, the right size, the right length and covered with concrete on every side. Once the concrete is in, nobody can see it, so the inspection before the pour is the only check there ever is.

Purpose of rebar

  • Takes tension that concrete cannot carry
  • Controls cracking from shrinkage and load
  • Ties footings, walls, slabs and stairs together
  • Strengthens corners, openings and transitions

Rebar sizes and types in Canada

Canadian bars are named by an "M" number that is close to the diameter in millimetres, and the bars are made to CSA G30.18.

BarDiameterAreaMass
10M11.3 mm (0.44 in)100 mm²0.785 kg/m (0.53 lb/ft)
15M16.0 mm (0.63 in)200 mm²1.570 kg/m (1.06 lb/ft)
20M19.5 mm (0.77 in)300 mm²2.355 kg/m (1.58 lb/ft)
25M25.2 mm (0.99 in)500 mm²3.925 kg/m (2.64 lb/ft)
30M29.9 mm (1.18 in)700 mm²5.495 kg/m (3.69 lb/ft)
35M35.7 mm (1.41 in)1,000 mm²7.850 kg/m (5.27 lb/ft)
  • 10M and 15M are the common house-and-small-building bars. 25M and up is commercial, industrial and civil work.
  • Old US sizes on older drawings are not the same. A US #4 is 1/2 in (12.7 mm), smaller than 15M (16.0 mm). Do not swap them.
  • Grade: normally 400 MPa, either weldable (400W) or regular (400R). Use what the drawings call for.
  • Coated or special steel: epoxy-coated, galvanized or stainless where the drawings require it for corrosion.
Confirm

The sizes above are from a secondary table that matches the usual CSA G30.18 values. Check them against the standard and the bar schedule on your drawings. Never swap a bar size or grade without the engineer's approval.

Concrete cover

Three cutaways side by side showing steel in a footing, a wall and a slab, each held off the soil or the form face by supports so that concrete covers the steel on every side.
Cover in a footing, a wall and a slab. Reinforcing steel is held off the soil and the form faces by supports, so concrete covers it on every side. Cover protects the steel from moisture and fire. Required cover varies with exposure, so check CSA A23.1 and your drawings. Not to scale.

Cover is the concrete between the steel and the outside face. It stops water and air reaching the steel and protects it in a fire. More exposure means more cover.

  • Cast against soil (footings): commonly 75 mm (3 in).
  • Interior slabs: as little as 20 mm (3/4 in).
  • Formed faces exposed to weather or soil (walls, exterior slabs): in between, depending on bar size and exposure.

Example. Bottom steel in a footing cast on soil with 75 mm cover sits on chairs 75 mm (3 in) high.

Confirm

The 75 mm and 20 mm figures are quoted in a secondary summary of CSA A23.1 Table 17. The in-between values were not verified. Cover depends on bar size, exposure class and member type (CSA A23.1 and A23.3). The engineer's drawings and the code decide for your job.

Bar supports

  • Plastic chairs under mesh and bars in slabs
  • Concrete blocks (dobies) under footing bars
  • Continuous chairs for mats and heavy bars
  • Wall spacers to keep bars off the form face
  • Never use wood, rocks, bricks or debris (see Rebar Chairs and Spacers)

Counting bars and weight

Bars at a spacing along a length: spaces = length ÷ spacing, and bars = spaces + 1. Weight = total length × mass per metre.

Wall. A 12 m (39 ft 4 in) wall with vertical 15M bars at 400 mm (15 3/4 in) on centre: 12 ÷ 0.4 = 30 spaces, so 31 bars. At 2.4 m (7 ft 10 in) each that is 74.4 m, and 74.4 × 1.57 = 116.8 kg, about 257 lb.

Footing. Two continuous 15M bars along a 30 m (98 ft) footing: 60 m × 1.57 = 94.2 kg, about 208 lb, before laps and waste.

The spacing and bar size here are examples. The drawings or the bar schedule give yours.

Where the steel goes

Footings

Many house footings are unreinforced under Part 9, so do not add or leave out bars on your own. Follow the drawings: longitudinal bars in the middle of the width on supports, tied to the dowels that connect the wall, corner bars at every turn, splices at the length the drawings give.

Foundation walls

Vertical bars tied to the footing dowels, horizontal bars at the specified spacing, extra bars around openings and at corners, and spacers to hold cover on both faces.

Slabs and pads

Welded wire mesh or bars, as drawn, on chairs at the height the drawings say, with perimeter bars at thickened edges and dowels where the slab ties into a wall.

Stairs and landings

Bars in the treads and risers, landing mats tied into the stair steel, dowels to tie to slabs or walls, and extra bars at nosings.

Retaining walls

Vertical bars closer together near the bottom, horizontal bars as drawn, corner bars at turns and steps, and top bars for caps or slab connections.

Lap splices and tying

A splice passes the load from one bar to the next. A splice that is too short is a weak link you cannot see.

  • Use the splice length on the drawings. It depends on bar size and concrete.
  • Stagger splices where you can, and do not splice in high-stress locations unless designed.
  • Tie the splice at both ends.
  • Use tie wire and a tying tool, firm but not so tight the bar moves out of position.
  • Keep wire ends turned away from the form face, and make sure bars cannot shift while concrete goes in.

Alignment and inspection

  • Check spacing with a tape.
  • Check cover at several points, at corners and at openings.
  • Straight, level bars, held up by supports.
  • Dowels aligned for the wall or column above.
  • Look at every corner and opening.

Common mistakes

  • Rebar touching soil or the form
  • Wrong spacing
  • Missing corner bars
  • Splices too short
  • Rebar floating or pushed down during the pour
  • Missing or misaligned dowels
  • Wrong bar size or grade
Pro note

Concrete hides everything, so check twice before the pour. Bars are easier to adjust at the dowels than at the pour. Spend extra time at corners and openings, because that is where cracks start.

Weather note

Cold makes steel stiffer and harder to bend. Mud on bars can hurt the bond, so clean off mud, oil and form release before the pour. Hot sun can overheat plastic chairs.

What the inspector looks at

Bar size and spacing, cover, splices, dowels, corners and openings, and whether the steel matches the drawings. The inspection happens before the pour, so book it ahead.

✅ Check yourselfTap a question
A drawing says 15M bars. What is the nominal diameter, and is it the same as a US #4 bar?
15M is 16.0 mm (0.63 in). A US #4 bar is 1/2 in (12.7 mm), which is smaller. The two are not interchangeable. Never swap bar sizes without the engineer's approval.
Two continuous 15M bars run the length of a 30 m (98 ft) footing. What do they weigh, before laps and waste?
2 × 30 = 60 m. 15M weighs 1.570 kg/m, so 60 × 1.57 = 94.2 kg, about 208 lb.
A 12 m (39 ft 4 in) wall has vertical 15M bars at 400 mm (15 3/4 in) on centre. How many bars?
12 ÷ 0.4 = 30 spaces, so 30 + 1 = 31 bars. If each is 2.4 m long, that is 31 × 2.4 = 74.4 m, or 116.8 kg (about 257 lb) of 15M.
A footing is cast against soil. What cover is commonly used, and how high is the chair?
The commonly quoted value is 75 mm (3 in) for concrete cast against soil. The chair holds the bottom bar 75 mm off the soil, so the chair is 75 mm high. Check CSA A23.1 and your drawings.
The bars look right but one footing dowel is 40 mm (1 1/2 in) out of position. What do you do?
Fix it before the pour. Dowels are easier to adjust before the wall steel goes on. If the fix needs a change to the drawing, the engineer decides.
What hazard is on every vertical bar end?
Impalement. Cap or guard vertical bar ends where people work above or beside them, and watch where you walk.
🧰 Gear for this stepMust-haveRent itNice to have
  • Must-haveLayout and measuring:
  • Must-haveCutting: bolt cutters or a hand rebar cutter for 10M and 15M bars (have heavier bars cut and bent by the supplier to the bar schedule)
  • Must-haveBending: a hand bar bender (hickey) and a bending bench for field bends the drawings allow
  • Must-haveTying:
  • Must-haveSupports:
  • Must-haveProtection: rebar caps or guards on vertical bar ends where people work above or beside them
  • Must-haveChecking:
  • Must-havePPE: hard hat (CSA Z94.1), safety glasses (CSA Z94.3), green-triangle boots (CSA Z195), gloves and hearing protection, cut-resistant where possible, plus CSA Z259 fall arrest where work is at 3 m (10 ft) or more
👷 Who can do thisTap your level
Home DIY
A capable owner can tie bars to a clear drawing and set chairs. Do not change bar size, spacing or grade, and do not skip steel that the drawings call for. Have an engineer or the inspector review structural or engineered concrete before the pour. Cap vertical bars, because impalement is a real hazard.
Laborer or helper
Carry, sort and tie only the bars you are shown. Cap vertical bars or watch where you walk, because impalement is a real hazard. Do not bend, cut or swap a bar without asking. Report a bar that looks wrong to your lead.
1st-year apprentice
You can cut, bend within limits, place, tie and support bars under supervision. Learn bar sizes, cover, splice length and how to read a bar schedule first.
Apprentice, 2nd to 4th year
Place and tie bars to the bar schedule, and learn cover, splices and dowel alignment. Check spacing with a tape before you move on. Do not change a bar size, grade or spacing. Tell your journeyperson about any spacing or cover error.
Journeyperson
You own placement against the drawings, cover, splices and dowel alignment, and the check before inspection. Stop-work triggers: any change to bar size, spacing or grade (the engineer decides), cover that cannot be met, or spacing errors found at the check. Fix these before the pour.
Lead hand or foreman
Check placement against the drawings before you call the inspector, including cover and dowel alignment. Make sure vertical bars are capped. Hold the pour for any change in bar size, spacing or grade until the engineer decides. Photograph the steel before it is hidden.
Contractor or business owner
Price steel, supports, labour and inspection time. Keep the bar schedule, photos and inspection record in the job file. Ask your lawyer or insurer who carries the cost of steel found wrong after the pour.
Starting a new business
Learn to read a bar schedule before you quote. Price steel, supports and re-work, and ask your building department when inspection of reinforcement is required. Subcontract engineered steel until you have the experience, and keep the engineer's letter.
By Province:

Reinforcing steel in Canada is made to CSA G30.18. Cover and splices come from CSA A23.1 and A23.3 and from the engineer's drawings, and house foundations follow NBC Part 9 as each province adopts it. Rebar capping and fall protection are provincial OHS matters.

  • All provinces and territories: the bar sizes and the drawings are the same. Ask your local authority when reinforcement is inspected, and your provincial OHS regulator about capping vertical bars.
  • See Permits and Approvals for the inspection stops, and Canada by Province for the comparison.
Sources:

Last reviewed October 2026. General information, not engineering or legal advice.