Elevation and Layout

Written for Canada. Plans are metric, but many crews and suppliers work in feet and inches, so this site gives both: millimetres and metres, with feet and inches beside them. Codes are the National Building Code of Canada 2020 (NBC 2020) Part 9 as your province adopts it. A number marked Confirm has not been checked against every province, so check it with your own authority before you act on it.

Reviewed by a working tradesman with 17+ years in the field.

Some links on this site are affiliate links. If you buy through them we may earn a commission at no extra cost to you. Affiliate disclosure

Move the drawings onto the ground: position, squareness and elevation, set from a benchmark that does not move.

I am a:

Tap your level and the boxes below open to the advice for you. Remembered on this device.

What it isMoving the drawings onto the ground: position, squareness and elevation.
Why it mattersIf layout or elevation is wrong, every trade after you pays for it.
The hard ruleNever guess a property line, and never move a pin or benchmark.
Two checks3-4-5 for one corner, equal diagonals for the whole rectangle.

By the end you can

  • Explain what pins, setbacks and benchmarks are and who sets each one.
  • Build batter boards and run string lines that survive the excavation.
  • Square a footprint with 3-4-5 and equal diagonals, and work out the diagonal.
  • Set and check elevations from a benchmark, and test a laser with a two-peg test.
  • Name the common layout mistakes and when to stop and call a surveyor.
Stop and read

Never move a pin, stake or benchmark, and never guess a property line. If pins are missing, disturbed or in doubt, or the building sits near a line or a floodplain, stop and have a licensed land surveyor re-establish them. Keep clear of excavators and trucks while you set stakes, and wear your hard hat and hi-vis when machines are working.

The big idea

Layout moves the drawings onto the ground. If the layout or elevation is wrong, every trade after you pays for it: footings in the wrong spot, a building that does not fit its setbacks, floors that do not meet the door sills. Layout does five jobs:

  • Transfers the drawings to the ground
  • Sets the finished floor elevation (FF)
  • Sets footing, wall, slab and column elevations
  • Squares and aligns the footprint
  • Leaves permanent control points for the trades that follow

Survey, pins and setbacks

  • Property pins are survey markers at the legal corners of the lot. If they are missing, disturbed or in doubt, have a licensed land surveyor re-establish them before you lay out near a line. In BC that is a BC Land Surveyor.
  • Setbacks come from the zoning bylaw and are measured from the lot lines. A permit can be refused, or a stop-work order issued, for a structure that is too close.
  • Some local governments require a survey certificate after the foundation is formed or poured, to confirm setbacks before framing starts. Ask whether yours does.
  • Sites in a floodplain can have a required minimum elevation for the lowest floor, called a flood construction level, set by local bylaw.
Confirm

Whether your municipality requires a post-foundation survey certificate, and what flood construction levels apply to your lot, depends on the local government. Ask the building department. Neither requirement is universal.

Benchmarks and control points

  • Primary benchmark (BM): a fixed elevation reference that will not move, such as a curb, a set pin, a building corner or a rock.
  • Secondary benchmarks: backups placed around the site.
  • Control points: gridlines, centrelines, offsets and corner points.

Find out which datum the drawings use. Some are tied to real geodetic elevations. Others use an arbitrary site number like 100.00 m (or 100.00 ft). Never mix them. Protect your benchmark, because if it moves the whole building moves.

Finished floor elevation (FF)

  • Confirm FF from the approved drawings.
  • Transfer it from the benchmark with a laser level.
  • Mark it on stakes, batter boards or a fixed object.
  • Use it to find footing elevation, top of wall, slab base, door thresholds, driveway slope and deck or landing heights.

Lasers and grade rods

Used to set footing depth, top-of-wall elevation, slab base, pad elevation, step-downs and trench depth. On commercial and civil work a total station is used for high-accuracy layout.

  • Check the laser with a two-peg test before you rely on it (below).
  • Re-check the height of instrument (HI) on the benchmark every time the tripod is moved.
  • A grade rod can read in millimetres or in feet, tenths and hundredths of a foot. Know which one yours is.

Two-peg test

Set two pegs about 30 m (100 ft) apart. The test finds whether the laser is truly level.

  1. Set up in the middle. Put the laser halfway between the pegs, 15 m (50 ft) from each. Read the rod on peg A and peg B. Any laser error is the same at both pegs, so it cancels. The difference is the true difference in height.
  2. Move to one end. Set the laser about 1 m (3 ft) from peg A, on the line. Read both pegs again.
  3. Compare. Compare the difference between the two readings from the new setup with the true difference from step 1. The gap is the laser error over the extra distance.
  4. Judge it. Compare the error with the accuracy the maker states for your laser. If it is worse, do not rely on it. Get it checked or calibrated.

Example. Setup 1: rod on A reads 1.512 m, rod on B reads 1.438 m. B is higher by 1.512 − 1.438 = 0.074 m. Setup 2, near A: A reads 1.420 m and B reads 1.341 m, so B looks higher by 0.079 m. The error is 0.079 − 0.074 = 0.005 m, or 5 mm over about 29 m. In imperial that is about 3/16 in over 95 ft.

Batter boards

Batter boards hold your string lines outside the excavation, so the layout survives the digging.

A plan view and a side view of batter boards. In the plan, boards on stakes stand outside the excavation limit and string lines cross over the corner point. In the side view, a level board is fixed across two stakes, a string runs from it, and a plumb bob hangs from the string crossing to a pin that marks the corner.
Batter boards. Set them outside the dig and level the tops to a known elevation. Strings cross over the corner point, so the layout survives the digging. Re-check after rain, frost and machine traffic. Not to scale.
  1. Drive stakes at the corners. Place them accurately at the project corners.
  2. Set the batter board stakes outside. About 1.5 m (5 ft) out from each corner stake, drive 25 x 100 mm (1x4 in) stakes. Leave room for the trench and the machine.
  3. Build the boards. Each board is 1.2 to 1.5 m (4 to 5 ft) long, so the string stays clear of the trench. Level the tops to a known elevation.
  4. Run the strings. Stretch line between boards for wall edges, centrelines and footing lines. Use a line level or the laser to confirm it is level.
  5. Mark the string positions. Cut small kerfs in the boards so the strings can be restrung in exactly the same place.
  6. Transfer with a plumb bob. Hang the plumb bob from the string crossing to the pin to mark the corner. It takes two people.
  7. Re-check. Check the boards after rain, frost and machine traffic.

Squaring the structure

Two methods in plan view. On the left, stakes at a corner and at 900 and 1200 millimetre marks on two strings, with a tape across the diagonal that must read 1500 millimetres for a true right angle. On the right, a rectangle of four stakes with two diagonal tapes that must read the same.
Two ways to check square. The 3-4-5 triangle checks one corner. Equal diagonals check the whole rectangle. Use the bigger multiples over long distances.
  • 3-4-5: measure 3 units along one line and 4 along the other from the same corner. The diagonal between the marks must be 5. In metric use 900, 1200 and 1500 mm, or 3 m, 4 m and 5 m. In imperial use 3 ft, 4 ft and 5 ft. Bigger multiples such as 6-8-10 or 9-12-15 give more accuracy over distance.
  • Diagonals: on a rectangle, the two diagonals must be equal.
  • Laser alignment for long runs, and a total station for commercial and civil layout.

Working out the diagonal

Diagonal = √(length² + width²). For a 12 m × 8 m building: √(144 + 64) = √208 = 14.42 m. For a 40 ft × 26 ft building: √(1600 + 676) = √2276 = 47.71 ft, which is 47 ft 8 1/2 in (0.71 × 12 = 8.5 in). Measure both diagonals. If they match each other and match the number, the building is square and the size is right.

Elevation changes and step-downs

Mark these clearly before excavation or forming: garage step-downs, basement transitions, frost wall elevation changes, slab depressions (showers, mechanical rooms, elevator pits), loading docks and machine bases, and drainage channels.

  • Residential: footings, walls, slabs, columns, beam pockets.
  • Commercial: gridlines, column centres, shear walls, slab depressions.
  • Industrial: machine bases, anchor bolt templates, heavy pads.
  • Civil: centrelines, drainage slopes, culverts, utility depths.

The layout workflow

  1. Check the current drawings and the pins. Confirm the revision. Find the legal pins. Call a surveyor if any are missing or in doubt.
  2. Set the benchmark. Choose something that will not move, write its elevation, and photograph it.
  3. Set the corner stakes. Use the drawing dimensions and the setbacks.
  4. Square it. Use 3-4-5 at each corner and check both diagonals.
  5. Set the batter boards and strings. Outside the excavation, levelled to a known elevation.
  6. Transfer elevations. Set the laser on the benchmark, find the height of instrument, and mark FF and footing depths.
  7. Protect and re-check. Re-check after the dig, after rain and frost, and after machines have been working around the layout.

Common mistakes

  • A wrong or disturbed benchmark
  • A laser out of level, or reading from the wrong datum
  • Wrong offsets
  • Sagging string lines
  • Layout moved by the excavator
  • Reading the drawings wrong, or working from an old revision
  • Laying out from a neighbour's fence or a guess instead of the legal pins
  • Not re-checking after weather or machine movement

What the inspector or surveyor checks

  • Footprint dimensions match the drawings
  • Footing elevation is correct
  • Wall thickness and alignment
  • Elevations are consistent across the site
  • Setbacks to the property lines
Pro note

Protect the benchmark, then re-check your elevations after the dig, after rain and frost, and after heavy equipment moves around. Write the benchmark elevation on a stake and also on a nearby fixed object, and take a photo. When something looks off, the first question is always: did the reference move?

Weather note

Rain washes out marks. Frost shifts stakes and elevations. Heat makes string lines sag and lasers shimmer. Wind moves stakes and strings. Re-check after major weather.

✅ Check yourselfTap a question
The drawings give a 9 m × 12 m footprint. What must each diagonal measure to be square?
√(9² + 12²) = √(81 + 144) = √225 = 15 m. In feet, a 30 ft × 40 ft building has a 50 ft diagonal. Both diagonals must read the same.
The two diagonals read 15.00 m and 15.03 m. What do you do?
They do not match, so the footprint is not square. Find which corner is off, move it, and measure again. Ask the designer what tolerance the drawings allow.
A pin looks bumped by the excavator. Do you use it?
No. Stop and have a licensed land surveyor re-establish it before you lay out near a line. Never guess a property line.
Why set batter boards instead of leaving the corner stakes in?
The corner stakes get dug out. Batter boards sit outside the excavation and hold string lines that mark the corners and wall lines, so the layout survives digging.
You moved the laser to a new spot. What must you do before reading rods?
Re-check the height of instrument on the benchmark. A new setup is a new height, and the old one no longer applies.
Your laser reads 5 mm different over 29 m. Is that fine?
Compare it with the maker's stated accuracy. If it is worse than that, do not rely on it, and get it checked or calibrated. 5 mm is about 3/16 in.
🧰 Gear for this stepMust-haveRent itNice to have
  • Nice to haveLevelling:
  • Must-haveLevelling: a grade rod and a 4 ft (1.2 m) level
  • Must-haveMeasuring:
  • Must-haveMarking:
  • Must-haveBatter boards and stakes:
  • Must-haveLong-distance squaring: two long tapes for diagonals
  • Rent itA total station, which is used on commercial and civil layout
  • Must-haveHard hat (CSA Z94.1), safety glasses (CSA Z94.3), green-triangle boots (CSA Z195) and gloves
👷 Who can do thisTap your level
Home DIY
You can lay out a small shed, deck or garden structure with string, batter boards and the 3-4-5 check. Do not guess the property line. If pins are missing or the building is near a line or a floodplain, hire a licensed land surveyor first.
Laborer or helper
Hold the rod, carry stakes and keep the string lines undisturbed. Never move a pin, stake or benchmark. If something has been bumped or moved, say so right away. Learn what the 3-4-5 check does by watching it done.
1st-year apprentice
You can set stakes, run strings and shoot elevations under supervision. Learn to read the benchmark, the datum and the height of instrument before you move the laser.
Apprentice, 2nd to 4th year
Practise setting and checking stakes, then confirm each by a second route, such as diagonals. Learn to find the benchmark and the datum and record both on the sheet. Never move a pin, and flag any difference you cannot explain to your journeyperson.
Journeyperson
You own layout accuracy, the benchmark and the re-checks after weather and machine traffic. Your stop-work triggers are pins that are missing or disturbed, diagonals that do not match, or a revision you cannot confirm. Stop and get a surveyor or a written answer before you set footings.
Lead hand or foreman
Re-check pins, benchmark and diagonals at the start of each day, and again after rain, frost or machine work. Keep the crew off layout lines you set. Stop at the first pin that is missing or off and get the surveyor before footings. Never guess a property line.
Contractor or business owner
Price survey and re-staking, keep a dated record of benchmark elevations and photos, and confirm which pins and revision you worked from. A footing in the wrong place or over a setback is a costly rebuild. Ask your lawyer or insurer who carries the cost and liability.
Starting a new business
Hire a licensed land surveyor when pins are missing, disturbed or in doubt, or the building sits near a line. Learn what the survey sheet shows before you quote. Ask your building department which setbacks apply, and your insurer who pays when a building is placed wrong.
By Province:

Setbacks, survey certificates and flood construction levels come from local zoning and building bylaws, not from the building code. The footing inspection that checks your layout is a standard stop where inspection stages were verified (BC, SK, ON, NB, NS, PE and Whitehorse). Elsewhere, ask your local authority.

  • BC: local governments set permits and inspections. Survey certificate rules vary, so ask your building department.
  • SK: Saskatoon has a footing inspection after the pour and stripping. Regina has a foundation inspection after rebar and before pouring.
  • ON: notify the chief building official when ready to construct footings, and at substantial completion of footings and foundations before backfilling.
  • NB, NS, PE: footings and foundations are inspected before backfilling. PE needs 3 days notice. NL: municipal rules apply to houses.
  • YT: Whitehorse requires a foundation and under-slab inspection before backfill. NWT and Nunavut: ask the local authority.
  • AB, MB, QC: ask the local authority about survey and inspection requirements.

See Permits and Approvals for the stops, and Canada by Province for the comparison.

Sources:
  • Quikrete, Layout basics for slabs and footers (batter boards, 3-4-5, diagonals, string lines)
  • NPTEL, Two-peg test (the principle, for a surveyor's level; the laser version above follows the same logic)
  • Diagonal and 3-4-5 arithmetic is the Pythagorean theorem, calculated and re-checked.
  • Setbacks, survey certificates and flood levels: your local zoning and building bylaws. Inspection stops: see Permits and Approvals.

Last reviewed October 2026. General information, not engineering or legal advice.