Ground Prep and Excavation

Written for Canada. Plans are metric, but many crews and suppliers work in feet and inches, so this site gives both: millimetres and metres, with feet and inches beside them. Codes are the National Building Code of Canada 2020 (NBC 2020) Part 9 as your province adopts it. A number marked Confirm has not been checked against every province, so check it with your own authority before you act on it.

Reviewed by a working tradesman with 17+ years in the field.

Some links on this site are affiliate links. If you buy through them we may earn a commission at no extra cost to you. Affiliate disclosure

Prepare the site, dig to the right depth on the right ground, and be ready for the inspector.

I am a:

Tap your level and the boxes below open to the advice for you. Remembered on this device.

What it isPreparing the site and digging to the right depth, on the right ground, ready for the inspector.
The big ideaIf the ground is wrong, everything on top of it fights you for the life of the building.
The hard ruleLocates first. Nobody in a hole over 1.2 m (4 ft) unless it is protected.
Depth comes fromThe drawings, the frost depth and the code. Never a guess.

By the end you can

  • Prepare a site before the machine starts: locates, access, spoil, drainage.
  • Dig to a required depth using a laser and grade rod, and work out the rod reading.
  • Prepare a clean, level bearing surface the inspector will pass.
  • Keep water, frost and loose soil out of the bottom of the dig.
  • Name the stop-work triggers in an excavation.
Stop and read

Get your utility locates before the machine starts, and find the private lines yourself. Nobody enters a trench or excavation deeper than 1.2 m (4 ft) unless it has been sloped, benched, shored or boxed by a qualified person. Digging next to an existing building usually needs an engineer's advice. Your provincial regulator sets the legal depth, and it differs. See Canada by Province.

Site preparation

Before any excavation starts, the crew lead:

  • Confirms the property lines and setbacks. On a tight lot, have the pins located by a land surveyor.
  • Reviews the plans for footprint, elevations and drainage, using the current revision.
  • Locates utilities: public through the one-call service, and private (septic, well, buried power, irrigation) yourself.
  • Plans access for trucks, excavators and concrete, including the pump truck if one is needed.
  • Sets staging areas, spoil pile locations and material zones.
  • Puts temporary drainage and erosion control in place.

Inspectors and neighbours both ask the same thing: where is the water going? Have the answer before you dig.

Grading slope

The minimum slope away from the foundation is set by the drawings, your provincial code and sometimes the municipal lot-grading bylaw. A common rule of thumb is 5% for the first couple of metres, but we have not checked that number against the code. Use the number on your grading plan.

Utility coordination

  • Locate before you dig. Call your province's one-call service, allow at least 3 business days, and trace private lines yourself. See Permits and Approvals for numbers.
  • Hand-expose near the marks. The locate report lists hand-expose zones. Keep machines out of those zones until the line is exposed by hand or vacuum. Hand tools can still cut a line, so use a flat blade and never a pointed probe.
  • Get the servicing rules. Cover, separations and bedding come from the municipality and the utility owner, not from a national number.
  • Protect crossings and keep access clear for future work.

Access, safety and site control

  • Safe routes for workers and equipment, away from the dig.
  • Stable ramps, and ladders in trenches as your provincial OHS regulator requires.
  • Clear walk paths with no debris.
  • Spoil piles kept back from the edge. Several provinces say at least 1 m. See Spoil Pile Management.
  • Fencing or barriers around open excavations, especially near public walks and neighbours.
  • Signs for hazards and restricted areas.

Kinds of excavation

Footing trenches. Full basements and crawl spaces. Slab-on-grade over-excavation. Utility trenches. Driveway and sidewalk subgrade. Retaining wall excavations. Sump pits and drainage trenches. The rules for depth, spoil and exits apply to all of them.

The bearing surface

The footing needs ground that can carry the load and will not move. The model code is clear on the basics (NBC 9.12, BC 2012 text checked):

  • Foundation excavations go down to undisturbed soil (9.12.2.1).
  • Remove topsoil and vegetable matter under the building. The bottom of every excavation is free of all organic material (9.12.1.1).
  • Excavations are kept free of standing water (9.12.1.2).
  • The bottom is kept from freezing for the whole construction period (9.12.1.3).

In practice that means:

  • Identify the soil. See Soil Types and Bearing.
  • Strip topsoil, roots and stumps.
  • Over-excavate soft, loose or disturbed areas and replace with compacted granular fill, as the engineer specifies.
  • Never place a footing on frozen ground, ground softened by water, or loose backfill.
  • Have the engineer or geotechnical consultant confirm the bearing surface if the drawings require it.
A cross-section of an excavation. Topsoil is stripped and stockpiled on the left. The sides slope down to a flat bearing surface of clean, level, undisturbed ground. A laser on a tripod sends a red dashed beam to a grade rod on the bearing surface. A benchmark stake stands on the left. A small sump pit sits at a low point.
What the inspector expects to see. Topsoil stripped, a clean level bearing surface, a protected benchmark, depth checked with a laser and rod, and a low point to pump from. The slopes of the walls follow the trench rules.

How deep?

Depth comes from the drawings, the frost depth and the code. It is never a guess.

The model code gives a minimum foundation depth that depends on soil, drainage and whether the space is heated (NBC 9.12.2.2 and Table 9.12.2.2). In the table, rock has no minimum, coarse-grained soil with good drainage has no minimum, and silt and clay often have to go below the depth of frost penetration, with 1.2 m shown for clay. Your local authority or engineer sets the frost depth for your site.

Confirm

Frost depth varies hugely across Canada, from the mild coast to the Interior, Prairies and north. We checked the structure of 9.12.2.2 against an older BC copy of the code, and the table text was partly garbled, so do not take a depth from this page. Get the number from your drawings or your building department, and never copy a depth from another town.

The excavation workflow

  1. Strip topsoil. Remove grass, roots and organic material. Topsoil is not load-bearing. Stockpile it separately for landscaping.
  2. Dig to depth. Use an excavator, skid steer or hand tools to suit the job. Check depth often with a laser and grade rod. Dig evenly across the footprint and stop short of final grade so the last bit is trimmed by hand. Do not over-dig. Backfilling the extra with loose soil is worse than leaving the original ground.
  3. Square and level. Check corners and edges with the laser. Check depth at several points. Remove high spots and loose soil. Leave the floor flat and consistent.
  4. Keep the walls safe. Slope, bench or support the walls as your provincial OHS regulation requires. Keep spoil and equipment back from the edge. Keep a safe way out within reach of every worker. Re-inspect after rain, frost and any change in the soil.
  5. Clean the base. Remove loose soil, rocks and mud by hand. Compact granular base where it is called for. Add gravel for drainage or stability only as specified.
  6. Manage water. Pump out standing water and let silty water settle before it leaves the site. Slope the dig to a low point for pumping. Keep surface water out of trenches.
  7. Get ready for the inspector. The dig is clean and clearly defined, shows footing locations and depths, has visible benchmarks and drainage intent, is safe to enter and measure, and has the approved drawings on site.

Worked example: setting the depth with a laser

The drawings put the underside of the footing at elevation 98.60. The benchmark is 100.00. You set the laser and put the rod on the benchmark: it reads 1.35 m.

  1. Height of instrument. 100.00 + 1.35 = 101.35. That is the elevation of the laser beam.
  2. Target rod reading at the footing bottom. 101.35 − 98.60 = 2.75 m.
  3. Check the dig. The rod on the bottom reads 2.62 m. That is 2.75 − 2.62 = 0.13 m too high, so dig 130 mm more.
  4. Over-dig check. A reading of 2.90 m means 150 mm too deep. Do not backfill it with loose soil. Call the engineer or building department for the fix.
  5. Record it. Write the benchmark, the reading and the date, and photograph the rod on the bottom.

The same job in feet

Many grade rods read in feet, tenths and hundredths of a foot, not inches. The benchmark is 100.00 ft and the rod on it reads 4.40 ft. The footing bottom is at 95.50 ft.

  1. Height of instrument. 100.00 + 4.40 = 104.40 ft.
  2. Target rod reading. 104.40 − 95.50 = 8.90 ft.
  3. Check the dig. The rod on the bottom reads 8.60 ft. That is 8.90 − 8.60 = 0.30 ft too high. 0.30 × 12 = 3.6 in, so dig about 3 5/8 in more.
  4. Tenths to inches. Tenths of a foot are not inches. 0.1 ft is 1.2 in, and 0.5 ft is 6 in. Multiply the decimal by 12.

Common mistakes

  • Digging before the locates are back.
  • Over-digging and filling with loose soil. The footing then bears on soil that can settle.
  • Pouring on a bottom that froze or got soaked.
  • Copying a frost depth from another town.
  • No plan for water. It collapses trench walls and fails inspections.
  • Spoil piled at the edge. It adds weight where the wall is weakest.
Weather note

Rain washes out graded areas, softens trench walls and saturates soil. Freeze-thaw loosens compacted fill. Heat dries the soil fast and raises dust. Cover exposed soil, keep temporary drainage working, and never pour on frozen or water-softened ground.

Pro note

Ground prep is where you solve problems before they become structural defects. Walk the site with the plans before you dig and ask: where does the water go, where do the trucks go, where are the utilities, and where does the inspector walk?

✅ Check yourselfTap a question
The laser sits at 101.35 and the footing bottom is 98.60. What should the rod read on the bottom?
101.35 − 98.60 = 2.75 m. When the rod reads 2.75 m on the bottom, you are at grade. Less than that, you are still too high.
You dug 100 mm too deep in one spot. What do you do?
Do not fill it with loose soil. Ask the engineer or building department what to use, which is usually compacted granular fill, because a footing on loose backfill can settle.
It rained overnight and there is 50 mm of water in the footing trench. Can the inspector pass it?
No. The code says excavations must be kept free of standing water (NBC 9.12.1.2). Pump it out, let silty water settle before it leaves the site, and re-check the bottom for softened soil.
The bottom of the dig froze last night. What now?
The code says the bottom of excavations must be kept from freezing during construction (NBC 9.12.1.3). Never place a footing on frozen ground. Thaw or remove it and re-inspect, or cover and protect it before it freezes.
Why is stopping short of final depth and trimming by hand good practice?
A machine bucket can disturb the soil you want to bear on. Hand trimming leaves the undisturbed surface the footing needs.
🧰 Gear for this stepMust-haveRent itNice to have
  • Must-haveLayout and measuring:
  • Rent itDigging (machine): a mini or full-size excavator or skid steer with trenching and cleanup buckets
  • Must-haveDigging (hand tools):
  • Rent itCompaction (machines): a plate compactor or jumping jack
  • Must-haveCompaction (hand tool): a hand tamper for the base
  • Rent itWater control: a submersible pump with hoses
  • Must-haveTarps and silt control for runoff
  • Must-haveUtility locating: the locate marks and plans from the one-call service, and flat-blade hand tools for exposing lines (never a pointed probe near gas or electric lines)
  • Must-haveTrench ladders
  • Rent itShoring panels or a trench box, supplied or designed as the regulation requires
  • Must-haveHard hat (CSA Z94.1), safety glasses (CSA Z94.3) and green-triangle safety footwear (CSA Z195)
  • Must-haveA respirator rated for the dust (CSA Z94.4), hearing protection and high-visibility apparel near machines
👷 Who can do thisTap your level
Home DIY
You can strip topsoil, lay out and hand-dig shallow areas, and manage water. Do not enter any trench or excavation deeper than 1.2 m (4 ft) unless a qualified person or engineer has sloped, shored or boxed it, and do not judge sloping or shoring yourself. Do not dig next to a building without an engineer's advice. Call the one-call service first. Hire an operator when machines are involved.
Laborer or helper
Work on the surface: clearing, hauling, hand trimming and keeping tools back from the edge. Never enter a trench deeper than 1.2 m (4 ft) that is not protected, and never decide a hole is safe. Stay clear of the machine, and stop and tell your lead if you see cracking or seepage.
1st-year apprentice
Help with layout, grade checking, hand trimming and pumping under supervision. Learn the locate marks, the trench rules and where to stand. Never stand in a trench while a trench box is moved, and never enter one deeper than 1.2 m (4 ft) that is not protected.
Apprentice, 2nd to 4th year
Take on grade checks, hand trimming and pump set-up under a journeyperson, and learn the locate marks and the daily check. You do not decide whether a trench is safe to enter. Keep out of any hole over 1.2 m (4 ft) without protection, and stop if the wall changes.
Journeyperson
You own the depth, the bearing surface and inspection readiness. Your stop-work triggers are soft, wet or organic bearing ground, cracking or seepage in a trench wall, and any hole over 1.2 m (4 ft) with no protection. Stop and call the engineer.
Lead hand or foreman
Make the locates, the daily trench check and the entry rule part of every shift, and keep a written log. Enforce the no-entry line (1.2 m on this site) unless the trench is sloped, shored or boxed by a qualified person. Pull everyone out on any stop-work trigger and call the engineer.
Contractor or business owner
Price locates, spoil removal, dewatering and trench protection. Check that operators and workers meet your provincial OHS and workers' compensation requirements, and keep your insurance current. Document locates, daily trench checks and engineer letters. Ask your lawyer or insurer who carries the liability.
Starting a new business
Learn your provincial excavation rules and locate service before buying a machine. Subcontract deep digging and shoring to an experienced operator until you have a trained competent person. Ask your workers' compensation board, regulator and insurer what you must register and document.
By Province:

The model code sets the rules for foundation depth and footings on suitable ground. Excavation safety and locates are provincial. The checked numbers are below. The full table is in Canada by Province.

  • BC: protect before entering an excavation over 1.2 m (s. 20.81). Locates: 3 full business days.
  • AB: Part 32 of the OHS Code. Our earlier notes say protection over 1.5 m, spoil 1 m back and exit within 8 m. Confirm in Part 32 before relying on it. Locates: 3 full business days.
  • SK: protect over 1.2 m, per the regulator's overview. Confirm the clause.
  • MB: slope 1:1 after the first metre over 1.5 m, spoil 1 m back, ladder over 1.5 m, 48 hours notice to the Department of Labour before work deeper than 1.5 m. Locates: they contact you within 3 business days.
  • ON: no entry over 1.2 m unless sloped, shored or boxed. Spoil and equipment 1 m back (s. 233). Ladders inside the protected area (s. 240).
  • QC: excavation means 1.2 m or more. Engineer-sealed plans to CNESST at 6 m or more. Locates: 4 working days.
  • NB, NS, PE, NL: 1.2 m (4 ft) protection triggers in the sources we found. Spoil: NB 1.2 m, NS 1 m, PE about 609 mm.
  • YT, NT, NU: YT slope or support over 1.2 m, spoil 0.6 m from a trench. NWT: notify the Chief Safety Officer before digging deeper than 5 m. NU: Confirm.
Sources:

Last reviewed October 2026. General information, not engineering or legal advice.